Foundations Dhiya
Construction progress
% complete per quarter
Sales velocity
Units sold per quarter (bar) · Cumulative booked (line)
Inventory drain
Available units over time
Show financial data (advance collected vs withdrawn)
Quarterly financials
₹ Crore — advance collected vs amount withdrawn this quarter
Quarter-wise Tower Data
No tower breakdown recorded for this quarter.
Project details
- Registration no.
- PRM/KA/RERA/1268/378/PR/301224/007329
- District
- Mysore
- Promoter
- Foundations Developers & Promoters
- Firm type
- Partnership Firm
- PAN
- AABFF5426G
- GSTIN
- 29AABFF5426G1ZI
- Total cost
- ₹4.82 Cr
Frequently Asked Questions
Based on K-RERA registered data for Foundations Dhiya
Is Foundations Dhiya RERA registered in Karnataka?
Yes. Foundations Dhiya is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1268/378/PR/301224/007329.
What is the RERA registration number of Foundations Dhiya?
The K-RERA registration number of Foundations Dhiya is PRM/KA/RERA/1268/378/PR/301224/007329.
What is the current construction status of Foundations Dhiya?
As of Q4 2025-26, Foundations Dhiya is 75% complete according to its latest K-RERA quarterly filing.
Are flats still available in Foundations Dhiya?
As per the latest K-RERA filing (Q4 2025-26), Foundations Dhiya is sold out — no units are currently listed as available.
Are there any RERA complaints against Foundations Dhiya?
As per K-RERA data tracked by rera.watch, there are no complaints currently recorded against Foundations Dhiya.
How many RERA complaints does Foundations Developers & Promoters have?
Foundations Developers & Promoters, the builder/promoter of Foundations Dhiya, has 0 complaint(s) filed against them across all their K-RERA registered projects in Karnataka.
Who is the builder or developer of Foundations Dhiya?
Foundations Dhiya is developed by Foundations Developers & Promoters, a partnership firm registered with K-RERA in Mysore, Karnataka.
When did Foundations Dhiya last file a quarterly update with K-RERA?
Foundations Dhiya last filed a quarterly update for Q4 2025-26 on 2026-04-11. The project has submitted 2 quarterly report(s) on K-RERA to date.