Show financial data (advance collected vs withdrawn)
Quarterly financials
₹ Crore — advance collected vs amount withdrawn this quarter
Quarter-wise Tower Data
Filed: 2026-07-08 · Project 61% complete
Block 10093% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
93.0%
Block 10393% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
93.0%
Block 11391% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
91.0%
Block 11491% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
91.0%
Block 11591% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
91.0%
Block 11831% complete
Unit type
Total
Booked
Available
3 BHK
1
—
1
Parking
1
—
1
Floor completion
Floor 0
31.0%
Block 11931% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
31.0%
Block 12031% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
31.0%
Block 121100% complete
Unit type
Total
Booked
Available
4 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
100.0%
Block 12491% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
91.0%
Block 12591% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
91.0%
Block 12691% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
91.0%
Block 12891% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
91.0%
Block 1300% complete
Unit type
Total
Booked
Available
4 BHK
1
—
1
Parking
1
—
1
Floor completion
Floor 0
0.0%
Block 13144% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
44.0%
Block 13244% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
44.0%
Block 13344% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
44.0%
Block 13444% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
44.0%
Block 13518% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
18.0%
Block 13618% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
18.0%
Block 13723% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
23.0%
Block 13823% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
23.0%
Block 1390% complete
Unit type
Total
Booked
Available
4 BHK
1
—
1
Parking
1
—
1
Floor completion
Floor 0
0.0%
Block 1404% complete
Unit type
Total
Booked
Available
4 BHK
1
—
1
Parking
1
—
1
Floor completion
Floor 0
4.0%
Block 14128% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
28.0%
Block 14228% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
28.0%
Block 14328% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
28.0%
Block 14428% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
28.0%
Block 14528% complete
Unit type
Total
Booked
Available
3 BHK
1
—
1
Parking
1
—
1
Floor completion
Floor 0
28.0%
Block 14645% complete
Unit type
Total
Booked
Available
3 BHK
1
—
1
Parking
1
—
1
Floor completion
Floor 0
45.0%
Block 14747% complete
Unit type
Total
Booked
Available
3 BHK
1
—
1
Parking
1
—
1
Floor completion
Floor 0
47.0%
Block 14847% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
47.0%
Block 14931% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
31.0%
Filed: 2026-02-25 · Project 52% complete
Block 10090% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
90.0%
Block 10390% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
90.0%
Block 11391% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
91.0%
Block 11491% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
91.0%
Block 11591% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
91.0%
Block 11831% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
31.0%
Block 11931% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
31.0%
Block 12031% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
31.0%
Block 121100% complete
Unit type
Total
Booked
Available
4 BHK
1
1
0
4 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
100.0%
Block 12491% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
91.0%
Block 12591% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
91.0%
Block 12691% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
91.0%
Block 12889% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
89.0%
Block 1300% complete
Unit type
Total
Booked
Available
4 BHK
1
1
0
4 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
0.0%
Block 13130% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
30.0%
Block 13230% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
30.0%
Block 13328% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
28.0%
Block 13430% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
30.0%
Block 1356% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
6.0%
Block 1368% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
8.0%
Block 13714% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
14.0%
Block 13812% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
12.0%
Block 1390% complete
Unit type
Total
Booked
Available
4 BHK
1
1
0
4 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
0.0%
Block 1404% complete
Unit type
Total
Booked
Available
4 BHK
1
1
0
4 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
4.0%
Block 14128% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
28.0%
Block 14220% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
20.0%
Block 14320% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
20.0%
Block 14428% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
28.0%
Block 1456% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
6.0%
Block 14640% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
40.0%
Block 14735% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
35.0%
Block 14835% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
35.0%
Block 14911% complete
Unit type
Total
Booked
Available
3 BHK
1
1
0
3 BHK
1
1
0
Parking
1
1
—
Floor completion
Floor 0
11.0%
Unit Specifications
Unit type
Carpet area (sqft)
Units
3 BHK
1,791–1,897
58
4 BHK
2,790–3,461
8
Show escrow account details
Escrow Accounts
Bank
ICICI Bank
Branch
Residency Road
IFSC
ICIC0007429
70% Collection A/C
777705008650
Project details
Registration no.
PRM/KA/RERA/1270/302/PR/140223/005716
District
Ramanagara
Taluk
Bengaluru South
Promoter
SVAMITVA LANDMARKS
Firm type
Partnership Firm
PAN
ADDFS0350B
GSTIN
29ADDFS0350B1ZI
Total units
41
Total cost
₹65.08 Cr
Project start
2023-02-10
FAR sanctioned
0.61
Proposed completion
2027-12-31
Project address
Sy.No.60/6,7,8,9,10,11,12,95/1,2,3,4,5,6,7,8,95/9A,95/9B,95/10,12, Vaderahalli Village, Harohalli Hobli, Kanakapura Taluk, Ramanagara District.
Frequently Asked Questions
Based on K-RERA registered data for SVAMITVA TERRAVANA PHASE 1
Is SVAMITVA TERRAVANA PHASE 1 RERA registered in Karnataka?
Yes. SVAMITVA TERRAVANA PHASE 1 is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1270/302/PR/140223/005716.
What is the RERA registration number of SVAMITVA TERRAVANA PHASE 1?
The K-RERA registration number of SVAMITVA TERRAVANA PHASE 1 is PRM/KA/RERA/1270/302/PR/140223/005716.
What is the current construction status of SVAMITVA TERRAVANA PHASE 1?
As of Q4 2025-26, SVAMITVA TERRAVANA PHASE 1 is 61% complete according to its latest K-RERA quarterly filing.
Are flats still available in SVAMITVA TERRAVANA PHASE 1?
Yes. As per the latest K-RERA quarterly filing (Q4 2025-26), SVAMITVA TERRAVANA PHASE 1 has 7 unit(s) available for purchase.
How many flats have been sold in SVAMITVA TERRAVANA PHASE 1?
As per the latest K-RERA filing (Q4 2025-26), 26 out of 41 units in SVAMITVA TERRAVANA PHASE 1 have been sold or booked.
Are 3 BHK flats available in SVAMITVA TERRAVANA PHASE 1?
Yes. According to the latest K-RERA quarterly filing, there are 4 3 BHK unit(s) available in SVAMITVA TERRAVANA PHASE 1, Ramanagara.
Are 4 BHK flats available in SVAMITVA TERRAVANA PHASE 1?
Yes. According to the latest K-RERA quarterly filing, there are 3 4 BHK unit(s) available in SVAMITVA TERRAVANA PHASE 1, Ramanagara.
Are there any RERA complaints against SVAMITVA TERRAVANA PHASE 1?
As per K-RERA data tracked by rera.watch, there are no complaints currently recorded against SVAMITVA TERRAVANA PHASE 1.
How many RERA complaints does SVAMITVA LANDMARKS have?
SVAMITVA LANDMARKS, the builder/promoter of SVAMITVA TERRAVANA PHASE 1, has 0 complaint(s) filed against them across all their K-RERA registered projects in Karnataka.
Who is the builder or developer of SVAMITVA TERRAVANA PHASE 1?
SVAMITVA TERRAVANA PHASE 1 is developed by SVAMITVA LANDMARKS, a partnership firm registered with K-RERA in Ramanagara, Karnataka.
When did SVAMITVA TERRAVANA PHASE 1 last file a quarterly update with K-RERA?
SVAMITVA TERRAVANA PHASE 1 last filed a quarterly update for Q4 2025-26 on 2026-07-08. The project has submitted 2 quarterly report(s) on K-RERA to date.