Original research from K-RERA public filings — construction delays, builder compliance, and what the numbers actually show.
Data Analysis · July 2026 · Q1 2026-27

The Deadline That Means Nothing: How 59% of Bengaluru's RERA Projects Missed Their Completion Date

An analysis of 4,691 K-RERA registered projects finds that 2,768 — 59.0% — have passed their legally-declared completion date with no completion record on file. The average delay is 53 months.

59.0%
projects past deadline
53 months
average delay
2,768
projects affected
Read analysis →