Articles

Articles

Original research from K-RERA public filings — construction delays, builder compliance, and what the numbers actually show.
Data Analysis · September 2026

The Quiet Handover: 30 Bengaluru-Area Projects Changed Developers, and K-RERA's Own Website Almost Hid It

30 K-RERA registered projects have a different promoter of record today than the one buyers originally signed with — including four once sold under the Nitesh Estates name, a slice of Mantri Hills, and a project still marketed publicly as Ramky's own.

30
projects with a changed promoter
4
once sold under Nitesh Estates
5
recognizable developer groups
Read analysis →
Weekly Digest · 2026-08-16

This Week in K-RERA: 5 Signals Across Bengaluru Projects

5 notable K-RERA filing signals this week — including a construction milestone, a micromarket roundup, a new filing, a promoter comparison and a sold-out project — each checked against a real comparison point, not just reported in isolation.

Read analysis →
Data Analysis · August 2026 · Q1 2026-27

The Deadline That Means Nothing: How 68% of Bengaluru's RERA Projects Missed Their Completion Date

An analysis of 4,006 K-RERA registered projects finds that 2,727 — 68.1% — have passed their legally-declared completion date with no completion record on file. The average delay is 52 months.

68.1%
projects past deadline
52 months
average delay
2,727
projects affected
Read analysis →