The Deadline That Means Nothing: How 59% of Bengaluru's RERA Projects Missed Their Completion Date
An analysis of 4,691 K-RERA registered projects finds that 2,768 — 59.0% — have passed their legally-declared completion date with no completion record on file. The average delay is 53 months.
59.0%
projects past deadline
Read analysis →