Compare / KNS Unnati Phase III vs Silver Kites – Elite-1

KNS Unnati Phase III vs Silver Kites – Elite-1

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
Active
KNS Infrastructure Private Limited PRM/KA/RERA/1251/309/PR/230123/005654
28 complaints · 100% built
ESSENN INFRA TOWNSHIP PRIVATE LIMITED PRM/KA/RERA/1254/465/PR/271222/005561
KNS Unnati Phase III
No quarterly filings found for KNS Unnati Phase III yet — construction progress and sales data aren't available on K-RERA.
Silver Kites – Elite-1
Construction
100%
as of Q4 2025-26
Sold
of ? · +0 last qtr
Available
0
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
KNS Unnati Phase III
Complaints
0
on this project
Silver Kites – Elite-1
Complaints
28
on this project · 28 on ESSENN INFRA TOWNSHIP PRIVATE LIMITED overall
Builder track record
Across each promoter's other K-RERA registered projects
KNS Unnati Phase III
KNS Infrastructure Private Limited
3 other projects on K-RERA · 1 delivered (100% complete) · avg 100.0% complete
Silver Kites – Elite-1
ESSENN INFRA TOWNSHIP PRIVATE LIMITED
2 other projects on K-RERA · 2 delivered (100% complete) · avg 100.0% complete
KNS Unnati Phase III — escrow account details
Bank
Karur Vysya Bank Ltd.
Branch
CHANDRA LAYOUT
IFSC
KVBL0001350
70% Collection A/C
1350135000003368
Silver Kites – Elite-1 — escrow account details
Bank
Karnataka Bank Ltd.
Branch
Basavanagudi
IFSC
KARB0000090
70% Collection A/C
0902000110143001
KNS Unnati Phase III — details
Total cost
₹2.78 Cr
Project start
2022-08-20
Proposed completion
2025-08-20 overdue
Address
Kannalli Village, Yashawanthapura Hobli, Bangalore North Taluk, Bangalore
Silver Kites – Elite-1 — details
Total cost
₹2.93 Cr
Project start
2022-09-05
Proposed completion
2025-12-31
Address
Sy No.7/2,7/3,7/4 and 7/5, Nadipinayakanahalli Village, Jangamakote Hobli, , shidlaghatta Taluk, Chikkaballapura District , Sidlaghatta , Chikkaballapura, Karnataka - 562102