Compare / SOULSPRING PHASE 1 vs ADARSH PALM ACRES PHASE 3

SOULSPRING PHASE 1 vs ADARSH PALM ACRES PHASE 3

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
On track · 58% built
SHANKESHWAR LANDMARK LLP PRM/KA/RERA/1251/310/PR/220223/005735
On track · 3% built
Adarsh Nivaas Private Limited PRM/KA/RERA/1251/309/PR/181025/008181
SOULSPRING PHASE 1
Construction
58%
as of Q2 2026-27
Sold
170
of 172 · +5 last qtr
Available
62
ADARSH PALM ACRES PHASE 3
Construction
3%
as of Q2 2026-27
Sold
61
of 196 · +24 last qtr
Available
135
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
SOULSPRING PHASE 1
Complaints
0
on this project · 1 on SHANKESHWAR LANDMARK LLP overall
ADARSH PALM ACRES PHASE 3
Complaints
0
on this project · 3 on Adarsh Nivaas Private Limited overall
Builder track record
Across each promoter's other K-RERA registered projects
SOULSPRING PHASE 1
SHANKESHWAR LANDMARK LLP
1 other project on K-RERA · 0 delivered (100% complete) · avg 27.0% complete
ADARSH PALM ACRES PHASE 3
Adarsh Nivaas Private Limited
No other K-RERA registered projects on file for this promoter.
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
SOULSPRING PHASE 1
Delay risk trending ~23 month(s) past declared completion
Escrow 1 quarter(s) withdrawn with no matching progress
Promoter pattern 1 of 1 other projects show the same delay-risk pattern
ADARSH PALM ACRES PHASE 3
Escrow 1 quarter(s) withdrawn with no matching progress
SOULSPRING PHASE 1 — escrow account details
Bank
Indian Bank
Branch
Richmond Circle
IFSC
IDIB000R018
70% Collection A/C
7316853156
ADARSH PALM ACRES PHASE 3 — escrow account details
Bank
ICICI Bank
Branch
Residency Road Bangalore
IFSC
ICIC 000742
70% Collection A/C
742905000548
100% A/C
742905000547
30% A/C
742905000549
SOULSPRING PHASE 1 — details
Total units
172
Total cost
₹473.83 Cr
Project start
2023-02-01
Proposed completion
2028-12-31
Address
SY. NO. 102/2, YARANDAHALLI VILLAGE, JIGINI HOBLI ,ANEKAL TALUK, ANEKAL, BENGALURU URBAN, KARNATAKA
ADARSH PALM ACRES PHASE 3 — details
Total units
196
Total cost
₹579.47 Cr
Project start
2025-09-10
Proposed completion
2031-09-30
Address
Sy no 201/1, 202/2, 215/1, 215/2, 217/1, 217/10 & 217/11 Gattihalli village , Sarjapura hobli , Anekal Taluk, Bangalore urban dist. Pin 560099