Compare / Sobha Galera vs OVER THE RAINBOW PHASE 1

Sobha Galera vs OVER THE RAINBOW PHASE 1

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
Sobha Galera
Bengaluru Urban · Bengaluru East
1 complaint · 100% built
SOBHA LIMITED PRM/KA/RERA/1251/446/PR/050123/005601
On track · 16% built
TOTAL ENVIRONMENT PROJECTS (INDIA) PRIVATE LIMITED PRM/KA/RERA/1254/460/PR/240424/006832
Sobha Galera
Construction
100%
as of Q1 2026-27
Sold
39
of 40 · +2 last qtr
Available
1
OVER THE RAINBOW PHASE 1
Construction
16%
as of Q1 2026-27
Sold
28
of 33 · +4 last qtr
Available
5
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Sobha Galera
Complaints
1
on this project · 224 on SOBHA LIMITED overall
OVER THE RAINBOW PHASE 1
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
Sobha Galera
SOBHA LIMITED
36 other projects on K-RERA · 8 delivered (100% complete) · avg 51.2% complete · 54 complaints across those projects
OVER THE RAINBOW PHASE 1
TOTAL ENVIRONMENT PROJECTS (INDIA) PRIVATE LIMITED
No other K-RERA registered projects on file for this promoter.
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
Sobha Galera
Escrow 1 quarter(s) withdrawn with no matching progress
Promoter pattern 2 of 35 other projects show the same delay-risk pattern
OVER THE RAINBOW PHASE 1
Delay risk no completion progress across filed quarters
Escrow 1 quarter(s) withdrawn with no matching progress
Sobha Galera — escrow account details
Bank
Punjab National Bank
Branch
21/15 LANDMARK M.G. ROAD
IFSC
PUNB0104610
70% Collection A/C
1046102900000043
OVER THE RAINBOW PHASE 1 — escrow account details
Bank
Standard Chartered Bank
Branch
Koramangala Branch
IFSC
SCBL0036073
70% Collection A/C
45505433819
100% A/C
45505433789
30% A/C
45505433797
Sobha Galera — details
Total units
40
Total cost
₹124.70 Cr
Project start
2023-04-01
Proposed completion
2026-12-31
Address
Sy No. 54/3, 55/1, 55/2, 58/1, 58/2, 58/3, 59/2, 59/3, 59/4, 59/5, 60/2, 61, 63/1 Hadosiddapura Village, and Sy. No 31/1 Chikkannelli Village
OVER THE RAINBOW PHASE 1 — details
Total units
33
Total cost
₹111.80 Cr
Project start
2024-05-01
Proposed completion
2030-02-28
Address
Sy.No. 133 and 172, Kuduvati Village, Nandhi Hobli , Chikkaballapura Taluk , Chikkaballapur , Chikkaballapura, Karnataka - 562103