Compare / NORTHERNSKY EXCELSA vs LUCENT

NORTHERNSKY EXCELSA vs LUCENT

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
On track · 75% built
Northern Sky Properties Private Limited PRM/KA/RERA/1257/334/PR/160223/005729
LUCENT
Dakshina Kannada · Mangalore
On track · 55% built
M/s MOHTISHAM COMPLEXES PVT LTD PRM/KA/RERA/1257/334/PR/101023/006310
NORTHERNSKY EXCELSA
Construction
75%
as of Q1 2026-27
Sold
74
of 133 · +0 last qtr
Available
59
LUCENT
Construction
55%
as of Q1 2026-27
Sold
54
of 130 · +2 last qtr
Available
76
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
NORTHERNSKY EXCELSA
Complaints
0
on this project
LUCENT
Complaints
0
on this project · 1 on M/s MOHTISHAM COMPLEXES PVT LTD overall
Builder track record
Across each promoter's other K-RERA registered projects
NORTHERNSKY EXCELSA
Northern Sky Properties Private Limited
1 other project on K-RERA · 1 delivered (100% complete) · avg 100.0% complete
LUCENT
M/s MOHTISHAM COMPLEXES PVT LTD
1 other project on K-RERA · 0 delivered (100% complete) · avg 74.0% complete
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
NORTHERNSKY EXCELSA
Delay risk no completion progress across filed quarters
Escrow 1 quarter(s) withdrawn with no matching progress
LUCENT
Delay risk construction progress far too slow to plausibly hit declared completion
Promoter pattern 1 of 1 other projects show the same delay-risk pattern
NORTHERNSKY EXCELSA — escrow account details
Bank
STATE BANK OF INDIA
Branch
B C ROAD
IFSC
SBIN0004608
70% Collection A/C
41405360094
LUCENT — escrow account details
Bank
STATE BANK OF INDIA
Branch
SME BRANCH
IFSC
SBIN4118
70% Collection A/C
42342847637
100% A/C
42342838270
30% A/C
42310513644
NORTHERNSKY EXCELSA — details
Total units
133
Total cost
₹91.34 Cr
Project start
2023-01-31
Proposed completion
2028-12-31
Address
Light House Hill Road, , Behind Tagore Park , Mangalore
LUCENT — details
Total units
130
Total cost
₹49.50 Cr
Project start
2023-08-15
Proposed completion
2027-07-30
Address
ATTAVAR, MANGALORE