Compare / PURSUIT OF A RADICAL RHAPSODY PHASE III vs IN THAT QUIET EARTH PHASE-2A

PURSUIT OF A RADICAL RHAPSODY PHASE III vs IN THAT QUIET EARTH PHASE-2A

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
0 complaints · 28% built
Total Environment Habitat Pvt. Ltd. PRM/KA/RERA/1251/446/PR/281222/005565
On track · 0% built
Total Environment Constructions Private Limited PRM/KA/RERA/1251/446/PR/310125/007467
PURSUIT OF A RADICAL RHAPSODY PHASE III
Construction
28%
as of Q1 2026-27
Sold
115
of 130 · +115 last qtr
Available
15
IN THAT QUIET EARTH PHASE-2A
Construction
0%
as of Q1 2026-27
Sold
of 120 · +0 last qtr
Available
120
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
PURSUIT OF A RADICAL RHAPSODY PHASE III
Complaints
0
on this project · 20 on Total Environment Habitat Pvt. Ltd. overall
IN THAT QUIET EARTH PHASE-2A
Complaints
0
on this project · 4 on Total Environment Constructions Private Limited overall
Builder track record
Across each promoter's other K-RERA registered projects
PURSUIT OF A RADICAL RHAPSODY PHASE III
Total Environment Habitat Pvt. Ltd.
1 other project on K-RERA · 0 delivered (100% complete) · avg 9.0% complete
IN THAT QUIET EARTH PHASE-2A
Total Environment Constructions Private Limited
1 other project on K-RERA · 0 delivered (100% complete) · avg 10.0% complete · 1 complaint across those projects
PURSUIT OF A RADICAL RHAPSODY PHASE III — escrow account details
Bank
STATE BANK OF INDIA
Branch
COMMERCIAL BRANCH, BANGALORE
IFSC
SBIN0004196
70% Collection A/C
42528977723
100% A/C
42528978524
30% A/C
42528978046
IN THAT QUIET EARTH PHASE-2A — escrow account details
Bank
ICICI Bank
Branch
Concourse, ITPL, Bangalore
IFSC
ICIC0000551
70% Collection A/C
777705212313
100% A/C
777705212312
30% A/C
777705212314
PURSUIT OF A RADICAL RHAPSODY PHASE III — details
Total units
130
Total cost
₹459.92 Cr
Project start
2022-12-01
Proposed completion
2029-12-01
Address
Sy. No. 170(P), 170/1A, 169/1 to 169/4, 176/3, 177, 172/1, 172/2, 175 (P) & 136/1 , Hoodi Village, KR Puram Hobli, Ward No. 82, Bangalore
IN THAT QUIET EARTH PHASE-2A — details
Total units
120
Total cost
₹416.56 Cr
Project start
2025-01-01
Proposed completion
2032-12-31
Address
Property Katha No. 28 , 46, 110,111 situated at Bileshivale Village, Bidarahalli Hobli, Bengaluru East Taluk, Bengaluru