Compare / Silver Kites – Elite-1 vs SILVER SPRINGS ENCLAVE PHASE 1

Silver Kites – Elite-1 vs SILVER SPRINGS ENCLAVE PHASE 1

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
28 complaints · 100% built
ESSENN INFRA TOWNSHIP PRIVATE LIMITED PRM/KA/RERA/1254/465/PR/271222/005561
On track · 80% built
M E J HOLDINGS (MOHAMMED HABIBULLA ABID) PRM/KA/RERA/1265/347/PR/100323/005788
Silver Kites – Elite-1
Construction
100%
as of Q4 2025-26
Sold
of ? · +0 last qtr
Available
0
SILVER SPRINGS ENCLAVE PHASE 1
Construction
80%
as of Q3 2025-26
Sold
of ? · +0 last qtr
Available
0
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Silver Kites – Elite-1
Complaints
28
on this project · 28 on ESSENN INFRA TOWNSHIP PRIVATE LIMITED overall
SILVER SPRINGS ENCLAVE PHASE 1
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
Silver Kites – Elite-1
ESSENN INFRA TOWNSHIP PRIVATE LIMITED
2 other projects on K-RERA · 2 delivered (100% complete) · avg 100.0% complete
SILVER SPRINGS ENCLAVE PHASE 1
M E J HOLDINGS (MOHAMMED HABIBULLA ABID)
No other K-RERA registered projects on file for this promoter.
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
Silver Kites – Elite-1
No risk signals from filed quarters.
SILVER SPRINGS ENCLAVE PHASE 1
No risk signals from filed quarters.
Silver Kites – Elite-1 — escrow account details
Bank
Karnataka Bank Ltd.
Branch
Basavanagudi
IFSC
KARB0000090
70% Collection A/C
0902000110143001
SILVER SPRINGS ENCLAVE PHASE 1 — escrow account details
Bank
Canara Bank
Branch
MALLESHWARAM
IFSC
CNRB0000409
70% Collection A/C
120002422350
Silver Kites – Elite-1 — details
Total cost
₹2.93 Cr
Project start
2022-09-05
Proposed completion
2025-12-31
Address
Sy No.7/2,7/3,7/4 and 7/5, Nadipinayakanahalli Village, Jangamakote Hobli, , shidlaghatta Taluk, Chikkaballapura District , Sidlaghatta , Chikkaballapura, Karnataka - 562102
SILVER SPRINGS ENCLAVE PHASE 1 — details
Total cost
₹1.71 Cr
Project start
2023-01-01
Proposed completion
2025-12-30 overdue
Address
Sy No. 196/1 - 1 Acre 26.12 Gunta,, Tornahalli Village , Kasaba Hobli, Maluru Taluk, Kolar District. , Maluru , Kolar, Karnataka - 563130