ADARSH LAKE RESERVA Phase 1 vs Concorde Eleve
Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
ADARSH LAKE RESERVA Phase 1
Bengaluru Urban · Bengaluru South
0 complaints · 0% built
M/s Adarsh Developers
PRM/KA/RERA/1251/310/PR/200123/005639
Concorde Eleve
Bengaluru Urban · Bengaluru South
On track · 16% built
Concorde Housing Corporation Pvt Ltd
PRM/KA/RERA/1251/446/PR/210325/007608
ADARSH LAKE RESERVA Phase 1
Construction
0%
as of Q2 2026-27
Sold
—
of 162
· +0 last qtr
Available
162
Concorde Eleve
Construction
16%
as of Q2 2026-27
Sold
21
of 142
· +1 last qtr
Available
121
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
ADARSH LAKE RESERVA Phase 1
Complaints
0
on this project · 24 on M/s Adarsh Developers overall
Concorde Eleve
Complaints
0
on this project · 2 on Concorde Housing Corporation Pvt Ltd overall
Builder track record
Across each promoter's other K-RERA registered projects
ADARSH LAKE RESERVA Phase 1
M/s Adarsh Developers
1 other project on K-RERA
· 0 delivered (100% complete)
· avg 75.0% complete
· 15 complaints across those projects
Concorde Eleve
Concorde Housing Corporation Pvt Ltd
7 other projects on K-RERA
· 3 delivered (100% complete)
· avg 63.4% complete
· 1 complaint across those projects
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
ADARSH LAKE RESERVA Phase 1
Escrow
3 quarter(s) withdrawn with no matching progress
Concorde Eleve
Delay risk
trending ~45 month(s) past declared completion
Promoter pattern
2 of 7 other projects show the same delay-risk pattern
ADARSH LAKE RESERVA Phase 1 — escrow account details
Concorde Eleve — escrow account details
ADARSH LAKE RESERVA Phase 1 — details
Concorde Eleve — details