Compare / Sobha Dream Gardens Phase 3 - Wing 3 and 4 vs FOLIUM BY SUMADHURA PHASE-III

Sobha Dream Gardens Phase 3 - Wing 3 and 4 vs FOLIUM BY SUMADHURA PHASE-III

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
2 complaints · 73% built
SOBHA LIMITED PRM/KA/RERA/1251/446/PR/200923/006271
On track · 52% built
SUMADHURA INFRACON PRIVATE LIMITED PRM/KA/RERA/1251/310/PR/250325/007625
Sobha Dream Gardens Phase 3 - Wing 3 and 4
Construction
73%
as of Q1 2026-27
Sold
286
of 304 · +0 last qtr
Available
16
FOLIUM BY SUMADHURA PHASE-III
Construction
52%
as of Q1 2026-27
Sold
133
of 297 · +13 last qtr
Available
164
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Sobha Dream Gardens Phase 3 - Wing 3 and 4
Complaints
2
on this project · 222 on SOBHA LIMITED overall
FOLIUM BY SUMADHURA PHASE-III
Complaints
0
on this project · 4 on SUMADHURA INFRACON PRIVATE LIMITED overall
Builder track record
Across each promoter's other K-RERA registered projects
Sobha Dream Gardens Phase 3 - Wing 3 and 4
SOBHA LIMITED
36 other projects on K-RERA · 8 delivered (100% complete) · avg 51.8% complete · 53 complaints across those projects
FOLIUM BY SUMADHURA PHASE-III
SUMADHURA INFRACON PRIVATE LIMITED
13 other projects on K-RERA · 0 delivered (100% complete) · avg 51.3% complete · 3 complaints across those projects
Sobha Dream Gardens Phase 3 - Wing 3 and 4 — escrow account details
Bank
KOTAK MAHINDRA BANK
Branch
MG road
IFSC
KKBK0008066
70% Collection A/C
2349105668
FOLIUM BY SUMADHURA PHASE-III — escrow account details
Bank
RATNAKAR BANK
Branch
RBL BANK
IFSC
RATN0000156
70% Collection A/C
409743857332
100% A/C
409743857333
30% A/C
409743857334
Sobha Dream Gardens Phase 3 - Wing 3 and 4 — details
Total units
304
Total cost
₹410.05 Cr
Project start
2024-04-01
Proposed completion
2031-12-31
Address
Survey No. 50, 51 & 54, Belahalli Village, Yelahanka Hobli
FOLIUM BY SUMADHURA PHASE-III — details
Total units
297
Total cost
₹435.59 Cr
Project start
2025-03-17
Proposed completion
2029-12-31
Address
BBMP Katha No 650/389 Sy No 47/1 47/2A 47/2B 48/3 48/4 47/3 48/1C Whitefiled Village K R Puram Hobli Bangalore East Taluk