Compare / Sobha Neopolis Phase 5 - W 5, 6 & 7 vs Arvind Forest Trails

Sobha Neopolis Phase 5 - W 5, 6 & 7 vs Arvind Forest Trails

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
2 complaints · 73% built
SOBHA LIMITED PRM/KA/RERA/1251/446/PR/200923/006271
On track · 53% built
Arvind SmartSpaces Limited PRM/KA/RERA/1251/308/PR/271023/006354
Sobha Neopolis Phase 5 - W 5, 6 & 7
Construction
73%
as of Q2 2026-27
Sold
289
of 304 · +3 last qtr
Available
13
Arvind Forest Trails
Construction
53%
as of Q2 2026-27
Sold
140
of 253 · +0 last qtr
Available
113
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Sobha Neopolis Phase 5 - W 5, 6 & 7
Complaints
2
on this project · 225 on SOBHA LIMITED overall
Arvind Forest Trails
Complaints
0
on this project · 7 on Arvind SmartSpaces Limited overall
Builder track record
Across each promoter's other K-RERA registered projects
Sobha Neopolis Phase 5 - W 5, 6 & 7
SOBHA LIMITED
37 other projects on K-RERA · 9 delivered (100% complete) · avg 55.9% complete · 57 complaints across those projects
Arvind Forest Trails
Arvind SmartSpaces Limited
1 other project on K-RERA · 1 delivered (100% complete) · avg 100.0% complete · 1 complaint across those projects
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
Sobha Neopolis Phase 5 - W 5, 6 & 7
Escrow 2 quarter(s) withdrawn with no matching progress
Promoter pattern 1 of 36 other projects show the same delay-risk pattern
Arvind Forest Trails
Delay risk construction progress far too slow to plausibly hit declared completion
Escrow 1 quarter(s) withdrawn with no matching progress
Sobha Neopolis Phase 5 - W 5, 6 & 7 — escrow account details
Bank
KOTAK MAHINDRA BANK
Branch
MG road
IFSC
KKBK0008066
70% Collection A/C
2349105668
Arvind Forest Trails — escrow account details
Bank
ICICI Bank
Branch
YELAHANKA
IFSC
ICIC0000411
70% Collection A/C
041105004994
100% A/C
018905013680
30% A/C
018905013679
Sobha Neopolis Phase 5 - W 5, 6 & 7 — details
Total units
304
Total cost
₹410.05 Cr
Project start
2024-04-01
Proposed completion
2031-12-31
Address
Sy nos - 51/1(P), 51/2(P), 52/1(P), 52/2(P)&53 at Yadavanahalli village, Attibele hobli, Anekal taluk, Bangalore, Karnataka
Arvind Forest Trails — details
Total units
253
Total cost
₹339.21 Cr
Project start
2023-06-01
Proposed completion
2029-06-30
Address
Sy.no.65/1, 67,68/1,68/2,69,70/1,70/2,70/3,70/5,70/6,70/7,71/1,71/2,71/3,71/4,72/2,72/3,73/1,73/2,73/3,73/4,73/5,73/6,73/7,73/8,73/9,74/1,74/2,74/4 , 75/3,75/4,75/5,76/1,76/2,76/3,76/4,76/5, 76/6, 76/7,76/8,77/1,77/3,77/4,77/5,79/3,80/3,80/4,81,82/4,82/5,82/6,82/7,88/4,95/2 & 96 , Anekal , Bengaluru Urban, Karnataka - 562125