Compare / GOOD EARTH OCTAVE vs GRAVITY ARANYA PHASE - 2

GOOD EARTH OCTAVE vs GRAVITY ARANYA PHASE - 2

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
GOOD EARTH OCTAVE
Bengaluru Urban · Bengaluru South
On track · 90% built
GOOD EARTH ECO COMMUNITIES PRIVATE LIMITED PRM/KA/RERA/1251/310/PR/060423/005851
On track · 72% built
GRAVITY ESTATES PRM/KA/RERA/1251/310/PR/271023/006360
GOOD EARTH OCTAVE
Construction
90%
as of Q1 2026-27
Sold
58
of 59 · +0 last qtr
Available
1
GRAVITY ARANYA PHASE - 2
Construction
72%
as of Q1 2026-27
Sold
21
of 72 · +0 last qtr
Available
51
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
GOOD EARTH OCTAVE
Complaints
0
on this project
GRAVITY ARANYA PHASE - 2
Complaints
0
on this project · 2 on GRAVITY ESTATES overall
Builder track record
Across each promoter's other K-RERA registered projects
GOOD EARTH OCTAVE
GOOD EARTH ECO COMMUNITIES PRIVATE LIMITED
1 other project on K-RERA · 0 delivered (100% complete) · avg 10.0% complete
GRAVITY ARANYA PHASE - 2
GRAVITY ESTATES
1 other project on K-RERA · 0 delivered (100% complete) · avg 98.0% complete · 2 complaints across those projects
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
GOOD EARTH OCTAVE
No risk signals from filed quarters.
GRAVITY ARANYA PHASE - 2
Delay risk trending ~4 month(s) past declared completion
Promoter pattern 1 of 1 other projects show the same delay-risk pattern
GOOD EARTH OCTAVE — escrow account details
Bank
HDFC
Branch
M G Road Bengaluru
IFSC
HDFC0000076
70% Collection A/C
57500001193076
GRAVITY ARANYA PHASE - 2 — escrow account details
Bank
HDFC
Branch
JAYANAGAR 8Th Block
IFSC
HDFC0002850
70% Collection A/C
57500001198641
100% A/C
57500001198523
30% A/C
57500001197839
GOOD EARTH OCTAVE — details
Total units
59
Total cost
₹186.76 Cr
Project start
2023-07-01
Proposed completion
2026-12-31
Address
Sy. Nos. 228(P), 229-1 & 229-2 , Kambipura Village , Bengaluru South , Bengaluru Urban, Karnataka - 560074
GRAVITY ARANYA PHASE - 2 — details
Total units
72
Total cost
₹160.84 Cr
Project start
2023-08-25
Proposed completion
2027-02-25
Address
NO.424/31,37,38, SY NO. 31, 37, & 38 CHUDENAPURA VILLAGE KENGERI HOBLI,BANGALORE SOUTH TALUK, BANGALORE ,WARD NO.198"