GOOD EARTH OCTAVE vs GRAVITY ARANYA PHASE - 2
Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
GOOD EARTH OCTAVE
Bengaluru Urban · Bengaluru South
On track · 90% built
GOOD EARTH ECO COMMUNITIES PRIVATE LIMITED
PRM/KA/RERA/1251/310/PR/060423/005851
GRAVITY ARANYA PHASE - 2
Bengaluru Urban · Bengaluru South
On track · 72% built
GRAVITY ESTATES
PRM/KA/RERA/1251/310/PR/271023/006360
GOOD EARTH OCTAVE
Construction
90%
as of Q1 2026-27
Sold
58
of 59
· +0 last qtr
Available
1
GRAVITY ARANYA PHASE - 2
Construction
72%
as of Q1 2026-27
Sold
21
of 72
· +0 last qtr
Available
51
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
GOOD EARTH OCTAVE
Complaints
0
on this project
GRAVITY ARANYA PHASE - 2
Complaints
0
on this project · 2 on GRAVITY ESTATES overall
Builder track record
Across each promoter's other K-RERA registered projects
GOOD EARTH OCTAVE
GOOD EARTH ECO COMMUNITIES PRIVATE LIMITED
1 other project on K-RERA
· 0 delivered (100% complete)
· avg 10.0% complete
GRAVITY ARANYA PHASE - 2
GRAVITY ESTATES
1 other project on K-RERA
· 0 delivered (100% complete)
· avg 98.0% complete
· 2 complaints across those projects
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
GOOD EARTH OCTAVE
No risk signals from filed quarters.
GRAVITY ARANYA PHASE - 2
Delay risk
trending ~4 month(s) past declared completion
Promoter pattern
1 of 1 other projects show the same delay-risk pattern
GOOD EARTH OCTAVE — escrow account details
GRAVITY ARANYA PHASE - 2 — escrow account details
GOOD EARTH OCTAVE — details
GRAVITY ARANYA PHASE - 2 — details