Compare / VM'S Lotuscity vs VM’s SRIVARI NEW CITY

VM'S Lotuscity vs VM’s SRIVARI NEW CITY

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
VM'S Lotuscity
Kolar · Hosakote
Active
VM BUILDER AND DEVELOPERS PRM/KA/RERA/1265/339/PR/060723/006050
On track · 26% built
VM BUILDER AND DEVELOPERS PRM/KA/RERA/1265/341/PR/100426/008579
VM'S Lotuscity
No quarterly filings found for VM'S Lotuscity yet — construction progress and sales data aren't available on K-RERA.
VM’s SRIVARI NEW CITY
Construction
26%
as of Q1 2026-27
Sold
—
of ? · +0 last qtr
Available
0
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
VM'S Lotuscity
Complaints
0
on this project
VM’s SRIVARI NEW CITY
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
VM'S Lotuscity
VM BUILDER AND DEVELOPERS
8 other projects on K-RERA · 0 delivered (100% complete) · avg 60.8% complete
VM’s SRIVARI NEW CITY
VM BUILDER AND DEVELOPERS
8 other projects on K-RERA · 0 delivered (100% complete) · avg 67.8% complete
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
VM'S Lotuscity
Promoter pattern 1 of 6 other projects show the same delay-risk pattern
VM’s SRIVARI NEW CITY
Promoter pattern 1 of 5 other projects show the same delay-risk pattern
VM'S Lotuscity — escrow account details
Bank
Canara Bank
Branch
Hoskote SME Branch
IFSC
CNRBO05580
70% Collection A/C
120002838231
VM’s SRIVARI NEW CITY — escrow account details
Bank
Canara Bank
Branch
Hoskote SME Branch
IFSC
CNRB0005580
70% Collection A/C
120033739578
100% A/C
120038283446
30% A/C
120001721633
VM'S Lotuscity — details
Total cost
₹12.62 Cr
Project start
2023-06-01
Proposed completion
2025-12-31 overdue
Address
Sy No.35/2, 36/1, 36/2, 36/3, 37/2, 38/1, 47/1, 47/2, Gadde Kannur Village Kasaba Hobli Kolar Taluk & Dist-563101. , Sy No.35/2, 36/1, 36/2, 36/3, 37/2, 38/1, 47/1, 47/2, Gadde Kannur Village Kasaba Hobli Kolar Taluk & Dist-563101. , Kolar , Kolar, Karnataka - 563101
VM’s SRIVARI NEW CITY — details
Total cost
₹11.14 Cr
Project start
2025-01-15
Proposed completion
2030-12-31
Address
Sy No. 2, 3/1, 3/2, 3/3, 4/1, 4/2, 5/1, 7/1, 7/2, Basavanatta Village, Kasaba Hobli, Srinivaspura Taluk, Kolar District, , Sy No. 2, 3/1, 3/2, 3/3, 4/1, 4/2, 5/1, 7/1, 7/2, Basavanatta Village, Kasaba Hobli, Srinivaspura Taluk, Kolar District, , Srinivasapura , Kolar, Karnataka - 563126