DNR PARKLINK PHASE 1 vs NIKHAR CELIO
Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
DNR PARKLINK PHASE 1
Bengaluru Urban · Bengaluru East
On track · 76% built
DNR CORPORATION PRIVATE LIMITED
PRM/KA/RERA/1251/446/PR/040823/006113
NIKHAR CELIO
Bengaluru Urban · Bengaluru East
On track · 17% built
NIKHAR ESTATES LLP
PRM/KA/RERA/1251/446/PR/280426/008605
DNR PARKLINK PHASE 1
Construction
76%
as of Q2 2026-27
Sold
315
of 356
· +0 last qtr
Available
41
NIKHAR CELIO
Construction
17%
as of Q2 2026-27
Sold
56
of 333
· +45 last qtr
Available
277
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
DNR PARKLINK PHASE 1
Complaints
0
on this project
NIKHAR CELIO
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
DNR PARKLINK PHASE 1
DNR CORPORATION PRIVATE LIMITED
1 other project on K-RERA
· 0 delivered (100% complete)
· avg 89.0% complete
NIKHAR CELIO
NIKHAR ESTATES LLP
No other K-RERA registered projects on file for this promoter.
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
DNR PARKLINK PHASE 1
Delay risk
trending ~5 month(s) past declared completion
Promoter pattern
1 of 1 other projects show the same delay-risk pattern
NIKHAR CELIO
Delay risk
construction progress far too slow to plausibly hit declared completion