Compare / PSP-PARAISO ENCLAVE PHASE-1 vs Paramount Rhapsody

PSP-PARAISO ENCLAVE PHASE-1 vs Paramount Rhapsody

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
Active
SMT. SHANTHI THANGAVELU PRM/KA/RERA/1268/378/PR/131023/006314
On track · 60% built
PARAMOUNT CONSTRUCTION VENTURES PVT LTD PRM/KA/RERA/1268/378/PR/201224/007311
PSP-PARAISO ENCLAVE PHASE-1
No quarterly filings found for PSP-PARAISO ENCLAVE PHASE-1 yet — construction progress and sales data aren't available on K-RERA.
Paramount Rhapsody
Construction
60%
as of Q1 2026-27
Sold
24
of 39 · +0 last qtr
Available
15
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
PSP-PARAISO ENCLAVE PHASE-1
Complaints
0
on this project
Paramount Rhapsody
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
PSP-PARAISO ENCLAVE PHASE-1
SMT. SHANTHI THANGAVELU
1 other project on K-RERA
Paramount Rhapsody
PARAMOUNT CONSTRUCTION VENTURES PVT LTD
1 other project on K-RERA · 0 delivered (100% complete) · avg 63.0% complete
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
PSP-PARAISO ENCLAVE PHASE-1
No risk signals from filed quarters.
Paramount Rhapsody
No risk signals from filed quarters.
PSP-PARAISO ENCLAVE PHASE-1 — escrow account details
Bank
Indian Bank
Branch
KUVEMPUNAGAR
IFSC
IDIB000K854
70% Collection A/C
7275008121
100% A/C
7275008121
30% A/C
7275008121
Paramount Rhapsody — escrow account details
Bank
HDFC
Branch
RICHMOND ROAD, BANGALORE
IFSC
HDFC0000523
70% Collection A/C
57500001531850
100% A/C
57500001533113
30% A/C
57500001532965
PSP-PARAISO ENCLAVE PHASE-1 — details
Total cost
₹31.26 Cr
Project start
2021-04-29
Proposed completion
2025-04-28 overdue
Address
Sy No-101/2a, 101/2b, 101/6, 135 & 232, K Hemmanahalli Village, , K Hemmanahalli Village , MYSORE , Mysore, Karnataka - 571130
Paramount Rhapsody — details
Total units
39
Total cost
₹32.12 Cr
Project start
2024-07-01
Proposed completion
2027-12-31
Address
No.2270/1, D-19, 19/1,19/2,19/3,19/4,19/5,19/6,19/7,19/8 , ‘Chittaranjan Mahal’ Vinoba Road , MYSORE , Mysore, Karnataka - 570012