Compare / Yesh Serenity Phase-03 vs HERBAL NATURE PHASE 2

Yesh Serenity Phase-03 vs HERBAL NATURE PHASE 2

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
Active
YESH DEVELOPERS AND PROMOTERS PRM/KA/RERA/1268/381/PR/300823/006199
On track · 70% built
GSS FARMS AND RESORTS PRIVATE LIMITED PRM/KA/RERA/1268/378/PR/200525/007760
Yesh Serenity Phase-03
No quarterly filings found for Yesh Serenity Phase-03 yet — construction progress and sales data aren't available on K-RERA.
HERBAL NATURE PHASE 2
Construction
70%
as of Q1 2026-27
Sold
of ? · +0 last qtr
Available
0
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Yesh Serenity Phase-03
Complaints
0
on this project
HERBAL NATURE PHASE 2
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
Yesh Serenity Phase-03
YESH DEVELOPERS AND PROMOTERS
2 other projects on K-RERA · 1 delivered (100% complete) · avg 100.0% complete
HERBAL NATURE PHASE 2
GSS FARMS AND RESORTS PRIVATE LIMITED
1 other project on K-RERA · 0 delivered (100% complete) · avg 80.0% complete
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
Yesh Serenity Phase-03
No risk signals from filed quarters.
HERBAL NATURE PHASE 2
Delay risk no completion progress across filed quarters
Promoter pattern 1 of 1 other projects show the same delay-risk pattern
Yesh Serenity Phase-03 — escrow account details
Bank
KOTAK MAHINDRA BANK
Branch
Jayalakshmi Puram V V Mohalla Mysore branch
IFSC
KKBK0008281
70% Collection A/C
7547949670
HERBAL NATURE PHASE 2 — escrow account details
Bank
BANK OF INDIA
Branch
Kuvempunagar Branch
IFSC
BKID0008432
70% Collection A/C
843222510000002
100% A/C
843222510000001
30% A/C
843222510000003
Yesh Serenity Phase-03 — details
Total cost
₹1.41 Cr
Project start
2023-07-07
Proposed completion
2025-09-22 overdue
Address
Gungralchatra Village, Ilwala Hobli
HERBAL NATURE PHASE 2 — details
Total cost
₹1.62 Cr
Project start
2025-02-01
Proposed completion
2029-12-31
Address
SY NO 44/4 (OLD SY NO 44/1) BYATHAHALLI VILLAGE , JAYAPURA HOBLI MYSORE TALUK , MYSORE , Mysore, Karnataka - 571311