Compare / PurpleBrick Avenue Garden - Phase 2 vs BASIL LAKEVIEW RESIDENCY

PurpleBrick Avenue Garden - Phase 2 vs BASIL LAKEVIEW RESIDENCY

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
Delivered · 100% built
PURPLEBRICK ESTATES LLP PRM/KA/RERA/1267/374/PR/130723/006066
On track · 50% built
SRI MAHAVISHNU BUILDERS PRM/KA/RERA/1270/302/PR/281025/008196
PurpleBrick Avenue Garden - Phase 2
Construction
100%
as of Q4 2025-26
Sold
of ? · +0 last qtr
Available
0
BASIL LAKEVIEW RESIDENCY
Construction
50%
as of Q1 2026-27
Sold
of ? · +0 last qtr
Available
0
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
PurpleBrick Avenue Garden - Phase 2
Complaints
0
on this project
BASIL LAKEVIEW RESIDENCY
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
PurpleBrick Avenue Garden - Phase 2
PURPLEBRICK ESTATES LLP
3 other projects on K-RERA · 2 delivered (100% complete) · avg 66.7% complete
BASIL LAKEVIEW RESIDENCY
SRI MAHAVISHNU BUILDERS
No other K-RERA registered projects on file for this promoter.
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
PurpleBrick Avenue Garden - Phase 2
No risk signals from filed quarters.
BASIL LAKEVIEW RESIDENCY
Delay risk no completion progress across filed quarters
PurpleBrick Avenue Garden - Phase 2 — escrow account details
Bank
KOTAK MAHINDRA BANK
Branch
M.G. Road Bangalore
IFSC
KKBK000806
70% Collection A/C
9845019621
BASIL LAKEVIEW RESIDENCY — escrow account details
Bank
IDFC FIRST BANK
Branch
Cunningham Bangalore
IFSC
IDFB0080176
70% Collection A/C
10227589572
100% A/C
10227589639
30% A/C
10227589640
PurpleBrick Avenue Garden - Phase 2 — details
Total cost
₹15.55 Cr
Project start
2023-07-10
Proposed completion
2028-06-10
Address
Sy No.224(P),223/1,223/3,220/2,221/3,228/3(P),228/5(P), at Belavadi village, , kasaba hobli, srirangapatna taluk, mandya district 571438 , Shrirangapattna , Mandya, Karnataka - 571438
BASIL LAKEVIEW RESIDENCY — details
Total cost
₹15.23 Cr
Project start
2023-01-01
Proposed completion
2027-08-31
Address
Sy.No. 8/1,8/2, 8/3,8/5,8/7,8/8,8/10,8/11,8/12,8/13,8/14,8/15,8/16,11/1, 11/2,12/1 & 12/2 , of Bannikuppe Village, Bidadi Hobli , Ramanagara , Ramanagara, Karnataka - 562159