Compare / Provident Ecopolitan Phase 2 vs Site and Service Scheme at Koppal

Provident Ecopolitan Phase 2 vs Site and Service Scheme at Koppal

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
On track · 24% built
Provident White Oaks LLP PRM/KA/RERA/1251/309/PR/110823/006163
Active
Karnataka Housing Board PRM/KA/RERA/1266/390/PR/310125/007464
Provident Ecopolitan Phase 2
Construction
24%
as of Q3 2025-26
Sold
126
of 128 · +126 last qtr
Available
2
Site and Service Scheme at Koppal
No quarterly filings found for Site and Service Scheme at Koppal yet — construction progress and sales data aren't available on K-RERA.
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Provident Ecopolitan Phase 2
Complaints
0
on this project · 2 on Provident White Oaks LLP overall
Site and Service Scheme at Koppal
Complaints
0
on this project · 2 on Karnataka Housing Board overall
Builder track record
Across each promoter's other K-RERA registered projects
Provident Ecopolitan Phase 2
Provident White Oaks LLP
4 other projects on K-RERA · 0 delivered (100% complete) · avg 42.0% complete · 2 complaints across those projects
Site and Service Scheme at Koppal
Karnataka Housing Board
4 other projects on K-RERA
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
Provident Ecopolitan Phase 2
No risk signals from filed quarters.
Site and Service Scheme at Koppal
No risk signals from filed quarters.
Provident Ecopolitan Phase 2 — escrow account details
Bank
HDFC
Branch
Kasturba Gandhi Marg Branch
IFSC
HDFC0000009
70% Collection A/C
57500001829112
100% A/C
57500001828938
30% A/C
99999920240011
Site and Service Scheme at Koppal — escrow account details
Bank
UNITED BANK OF INDIA
Branch
Koppal
IFSC
UBIN0909025
70% Collection A/C
520101080791812
100% A/C
520101080791812
30% A/C
520101080791812
Provident Ecopolitan Phase 2 — details
Total units
128
Total cost
₹78.17 Cr
Project start
2024-05-01
Proposed completion
2028-06-30
Address
Plot Nos R-4-Part-A & R-4-Part-B of Hardware Sector at Hitech, Defence & Aerospace Park, Bengaluru , Sy No Parts of 177 (Block No. 1,2 & 3) 72,73/1,73/2,73/3,73/4,74/1,74/2,74/3,74/4,75,76,78/2 & 78/3 , Bengaluru North , Bengaluru Urban, Karnataka - 562149
Site and Service Scheme at Koppal — details
Total cost
₹82.22 Cr
Project start
2021-07-29
Proposed completion
2025-12-31 overdue
Address
Sy. No. 367, 368, 369, 370, 371 Koppal Village, , Koppal Taluk, Koppal District , Koppal , Koppal, Karnataka - 583231