Compare / Saha Aspire vs ONEST GALAXY RESIDENTIAL LAYOUT PHASE-2

Saha Aspire vs ONEST GALAXY RESIDENTIAL LAYOUT PHASE-2

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
Saha Aspire
Mysore · MYSORE
On track · 98% built
ESS AND ESS INFRASTRUCTUREPRIVATE LIMITED PRM/KA/RERA/1268/378/PR/091123/006399
Active
ANVAR SADATH VALLANCHIRA PRM/KA/RERA/1253/286/PR/180124/006558
Saha Aspire
Construction
98%
as of Q1 2026-27
Sold
—
of ? · +0 last qtr
Available
0
ONEST GALAXY RESIDENTIAL LAYOUT PHASE-2
No quarterly filings found for ONEST GALAXY RESIDENTIAL LAYOUT PHASE-2 yet — construction progress and sales data aren't available on K-RERA.
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Saha Aspire
Complaints
0
on this project · 6 on ESS AND ESS INFRASTRUCTUREPRIVATE LIMITED overall
ONEST GALAXY RESIDENTIAL LAYOUT PHASE-2
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
Saha Aspire
ESS AND ESS INFRASTRUCTUREPRIVATE LIMITED
3 other projects on K-RERA · 1 delivered (100% complete) · avg 99.5% complete
ONEST GALAXY RESIDENTIAL LAYOUT PHASE-2
ANVAR SADATH VALLANCHIRA
1 other project on K-RERA
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
Saha Aspire
Delay risk no completion progress across filed quarters
Promoter pattern 1 of 2 other projects show the same delay-risk pattern
ONEST GALAXY RESIDENTIAL LAYOUT PHASE-2
No risk signals from filed quarters.
Saha Aspire — escrow account details
Bank
Union Bank of India
Branch
Ramakrishna Nagar
IFSC
UBIN0918598
70% Collection A/C
185921010000123
100% A/C
185921010000124
30% A/C
185921010000099
ONEST GALAXY RESIDENTIAL LAYOUT PHASE-2 — escrow account details
Bank
Axis Bank
Branch
NR MOHALLA
IFSC
UTIB0004543
70% Collection A/C
923020036845837
100% A/C
910020024457824
30% A/C
923020036598492
Saha Aspire — details
Total cost
₹2.96 Cr
Project start
2023-11-01
Proposed completion
2027-07-13
Address
Huyilalu Village, Ilawala Hobli, Mysore Taluk and Mysore District
ONEST GALAXY RESIDENTIAL LAYOUT PHASE-2 — details
Total cost
₹2.64 Cr
Project start
2023-11-01
Proposed completion
2024-09-30 overdue
Address
SY NO 172/2 ,172/3 , 178/3B & 178/6 OF GUNDLUPET (VIJAYAPURA VILLAGE) , KASABA HOBLI , Gundlupet , Chamarajanagar, Karnataka - 571111