Compare / SBR FLORENSO vs PSR PLATINUM

SBR FLORENSO vs PSR PLATINUM

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
SBR FLORENSO
Bengaluru Urban · Bengaluru East
On track · 60% built
SBR INFRA PRM/KA/RERA/1251/446/PR/091123/006405
PSR PLATINUM
Bengaluru Urban · Bengaluru East
On track · 0% built
M/s PSR BUILDERS AND DEVELOPERS PRM/KA/RERA/1251/446/PR/260226/008488
SBR FLORENSO
Construction
60%
as of Q4 2025-26
Sold
64
of 104 · +1 last qtr
Available
40
PSR PLATINUM
Construction
0%
as of Q1 2026-27
Sold
of 117 · +0 last qtr
Available
117
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
SBR FLORENSO
Complaints
0
on this project
PSR PLATINUM
Complaints
0
on this project · 4 on M/s PSR BUILDERS AND DEVELOPERS overall
Builder track record
Across each promoter's other K-RERA registered projects
SBR FLORENSO
SBR INFRA
No other K-RERA registered projects on file for this promoter.
PSR PLATINUM
M/s PSR BUILDERS AND DEVELOPERS
2 other projects on K-RERA · 1 delivered (100% complete) · avg 66.5% complete
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
SBR FLORENSO
Delay risk no completion progress across filed quarters
Escrow 1 quarter(s) withdrawn with no matching progress
PSR PLATINUM
Promoter pattern 1 of 2 other projects show the same delay-risk pattern
SBR FLORENSO — escrow account details
Bank
Bank of Maharashtra
Branch
Seegehalli
IFSC
MAHB0001682
70% Collection A/C
60463015504
100% A/C
60465971635
30% A/C
60465971748
PSR PLATINUM — escrow account details
Bank
Canara Bank
Branch
Hebbal
IFSC
CNRB0000425
70% Collection A/C
120036880132
100% A/C
120036880173
30% A/C
2673214000029
SBR FLORENSO — details
Total units
104
Total cost
₹98.79 Cr
Project start
2023-10-19
Proposed completion
2027-12-31
Address
Sy. Nos. 78/1, 78/2,78/3 , SEEGEHALLI VILLAGE, , Bengaluru East , Bengaluru Urban, Karnataka - 560067
PSR PLATINUM — details
Total units
117
Total cost
₹92.54 Cr
Project start
2025-12-01
Proposed completion
2029-12-31
Address
@ Sy no 170/2, Kodati Village , Varthur Hobli , Bengaluru East , Bengaluru Urban, Karnataka - 560035