Compare / ABHEE CELESTIAL CITY vs GRC SAPPHIRE SPRING - PHASE -1

ABHEE CELESTIAL CITY vs GRC SAPPHIRE SPRING - PHASE -1

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
On track · 64% built
NEXPLACE INFRASTRUCTURE PRM/KA/RERA/1251/308/PR/071123/006380
On track · 35% built
GRC Infra Pvt. Ltd. PRM/KA/RERA/1251/310/PR/030225/007478
ABHEE CELESTIAL CITY
Construction
64%
as of Q2 2026-27
Sold
208
of 399 · +8 last qtr
Available
191
GRC SAPPHIRE SPRING - PHASE -1
Construction
35%
as of Q2 2026-27
Sold
165
of 308 · +15 last qtr
Available
143
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
ABHEE CELESTIAL CITY
Complaints
0
on this project
GRC SAPPHIRE SPRING - PHASE -1
Complaints
0
on this project · 1 on GRC Infra Pvt. Ltd. overall
Builder track record
Across each promoter's other K-RERA registered projects
ABHEE CELESTIAL CITY
NEXPLACE INFRASTRUCTURE
No other K-RERA registered projects on file for this promoter.
GRC SAPPHIRE SPRING - PHASE -1
GRC Infra Pvt. Ltd.
1 other project on K-RERA · 0 delivered (100% complete) · avg 1.0% complete
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
ABHEE CELESTIAL CITY
No risk signals from filed quarters.
GRC SAPPHIRE SPRING - PHASE -1
No risk signals from filed quarters.
ABHEE CELESTIAL CITY — escrow account details
Bank
INDUSIND BANK
Branch
MG Road, Bangalore
IFSC
INDB0000008
70% Collection A/C
251213141981
100% A/C
251213141982
30% A/C
251213141980
GRC SAPPHIRE SPRING - PHASE -1 — escrow account details
Bank
Karnataka Bank Ltd.
Branch
Minerva Circle
IFSC
KARB0000062
70% Collection A/C
0062202600001501
100% A/C
0062202600001301
30% A/C
0062202600001401
ABHEE CELESTIAL CITY — details
Total units
399
Total cost
₹288.53 Cr
Project start
2023-10-18
Proposed completion
2029-06-30
Address
SY NO.24/2, 24/6, 24/8, 24/11, CHIKKAVADERAPURA VILLAGE, SARJAPURA HOBLI , ANEKAL TALUK, BANGALORE , Anekal , Bengaluru Urban, Karnataka - 560087
GRC SAPPHIRE SPRING - PHASE -1 — details
Total units
308
Total cost
₹273.06 Cr
Project start
2024-12-06
Proposed completion
2030-12-31
Address
SY 38/1 & 38/2 situated at choodasandra village sarjapur hobli anekal taluk bangalore, bangalore