Adira
Dakshina Kannada · Mangalore
On track · 60% built
Land Trades Builders and Developers Private Limited
PRM/KA/RERA/1257/334/PR/041223/006450
Milestone 25
Dakshina Kannada · Mangalore
On track · 14% built
LAND TRADES BUILDERS & DEVELOPERS
PRM/KA/RERA/1257/334/PR/291125/008291
Adira
Construction
60%
as of Q1 2026-27
Sold
12
of 23
· +0 last qtr
Available
11
Milestone 25
Construction
14%
as of Q1 2026-27
Sold
6
of 28
· +2 last qtr
Available
23
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Adira
Complaints
0
on this project
Milestone 25
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
Adira
Land Trades Builders and Developers Private Limited
1 other project on K-RERA
· 0 delivered (100% complete)
· avg 38.0% complete
Milestone 25
LAND TRADES BUILDERS & DEVELOPERS
2 other projects on K-RERA
· 0 delivered (100% complete)
· avg 5.0% complete