Compare / HARMONY NIRVANA Phase -I vs Foundations Bhagyashree

HARMONY NIRVANA Phase -I vs Foundations Bhagyashree

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
No quarterly filings
Tapovan Estates PRM/KA/RERA/1268/378/PR/291223/006519
On track · 56% built
Foundations Developers and Promoters PRM/KA/RERA/1268/378/PR/200325/007597
HARMONY NIRVANA Phase -I
No quarterly filings found for HARMONY NIRVANA Phase -I yet — construction progress and sales data aren't available on K-RERA.
Foundations Bhagyashree
Construction
56%
as of Q1 2026-27
Sold
8
of 45 · +0 last qtr
Available
37
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
HARMONY NIRVANA Phase -I
Complaints
0
on this project
Foundations Bhagyashree
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
HARMONY NIRVANA Phase -I
Tapovan Estates
No other K-RERA registered projects on file for this promoter.
Foundations Bhagyashree
Foundations Developers and Promoters
No other K-RERA registered projects on file for this promoter.
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
HARMONY NIRVANA Phase -I
No risk signals from filed quarters.
Foundations Bhagyashree
No risk signals from filed quarters.
HARMONY NIRVANA Phase -I — escrow account details
Bank
Union Bank of India
Branch
Ramakrishna Nagar
IFSC
UBIN0918598
70% Collection A/C
185921010000130
100% A/C
185921010000128
30% A/C
185921010000131
Foundations Bhagyashree — escrow account details
Bank
STATE BANK OF INDIA
Branch
V M Double road branch
IFSC
SBIN0040441
70% Collection A/C
43636110842
100% A/C
43648581411
30% A/C
34405636932
HARMONY NIRVANA Phase -I — details
Total units
47
Total cost
₹41.23 Cr
Project start
2023-05-01
Proposed completion
2026-05-01 overdue
Address
Harmony Nirvana, Hadajana Village, Varuna Hobli, Mysuru taluk,
Foundations Bhagyashree — details
Total units
45
Total cost
₹25.10 Cr
Project start
2025-01-01
Proposed completion
2027-03-31
Address