Heritage City I vs Foundations Sri Vilasa
Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
Foundations Sri Vilasa
Mysore · MYSORE
On track · 75% built
Foundations Developers & Promoters
PRM/KA/RERA/1268/378/PR/301224/007329
Heritage City I
No quarterly filings found for Heritage City I yet — construction progress and sales data aren't available on K-RERA.
Foundations Sri Vilasa
Construction
75%
as of Q1 2026-27
Sold
—
of ?
· +0 last qtr
Available
0
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Heritage City I
Complaints
0
on this project
Foundations Sri Vilasa
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
Heritage City I
Sathyanarayana Y S
2 other projects on K-RERA
Foundations Sri Vilasa
Foundations Developers & Promoters
1 other project on K-RERA
· 0 delivered (100% complete)
· avg 7.0% complete
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
Heritage City I
No risk signals from filed quarters.
Foundations Sri Vilasa
Delay risk
trending ~25 month(s) past declared completion
Escrow
1 quarter(s) withdrawn with no matching progress
Heritage City I — escrow account details
Foundations Sri Vilasa — escrow account details
Heritage City I — details
Foundations Sri Vilasa — details