Compare / VM INNOVATIVE TOWNSHIP vs VR VIRUPAKSHA TOWNSHIP

VM INNOVATIVE TOWNSHIP vs VR VIRUPAKSHA TOWNSHIP

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
On track · 78% built
VM VENTURES PRM/KA/RERA/1254/463/PR/040524/006866
On track · 10% built
VR BUILDERS AND DEVELOPERS PRM/KA/RERA/1265/343/PR/180226/008470
VM INNOVATIVE TOWNSHIP
Construction
78%
as of Q1 2026-27
Sold
—
of ? · +0 last qtr
Available
0
VR VIRUPAKSHA TOWNSHIP
Construction
10%
as of Q1 2026-27
Sold
—
of ? · +0 last qtr
Available
0
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
VM INNOVATIVE TOWNSHIP
Complaints
0
on this project
VR VIRUPAKSHA TOWNSHIP
Complaints
0
on this project · 1 on VR BUILDERS AND DEVELOPERS overall
Builder track record
Across each promoter's other K-RERA registered projects
VM INNOVATIVE TOWNSHIP
VM VENTURES
No other K-RERA registered projects on file for this promoter.
VR VIRUPAKSHA TOWNSHIP
VR BUILDERS AND DEVELOPERS
4 other projects on K-RERA · 0 delivered (100% complete) · avg 75.0% complete · 1 complaint across those projects
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
VM INNOVATIVE TOWNSHIP
Delay risk no completion progress across filed quarters
VR VIRUPAKSHA TOWNSHIP
Promoter pattern 1 of 1 other projects show the same delay-risk pattern
VM INNOVATIVE TOWNSHIP — escrow account details
Bank
Canara Bank
Branch
HOSKOTE SME
IFSC
CNRB0005580
70% Collection A/C
120026363798
100% A/C
120026363859
30% A/C
120025781461
VR VIRUPAKSHA TOWNSHIP — escrow account details
Bank
Canara Bank
Branch
HOSKOTE
IFSC
CNRB0005580
70% Collection A/C
120036555937
100% A/C
120036555924
30% A/C
5580201000128
VM INNOVATIVE TOWNSHIP — details
Total cost
₹13.51 Cr
Project start
2023-11-06
Proposed completion
2027-12-31
Address
Sy No. 47/3, 48/3, 48/4, 48/5, 49/3, 53, 54/2, 55, 56, 57, situated at Udamalodu Village, Kasaba Hobli,Gauribidanur Taluk, Chikkaballapur Dist , Sy No. 47/3, 48/3, 48/4, 48/5, 49/3, 53, 54/2, 55, 56, 57, situated at Udamalodu Village, Kasaba Hobli,Gauribidanur Taluk, Chikkaballapur Dist , Gauribidanur , Chikkaballapura, Karnataka - 561208
VR VIRUPAKSHA TOWNSHIP — details
Total cost
₹18.43 Cr
Project start
2025-10-03
Proposed completion
2027-12-31
Address
Sy NO 5/12, 6/2, 6/3, 6/4, 6/5, 7/1A, 7/1B, 7/2, 7/3, 7/4 and 11 , V Guttahalli Village, Avani Hobli, Mulbhagal , Mulabagilu , Kolar, Karnataka - 563131