Milestone 25 vs Adira
Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
Milestone 25
Dakshina Kannada · Mangalore
Delivered · 100% built
Land Trades Builders and Developers
PRM/KA/RERA/1257/334/PR/220424/006823
Adira
Dakshina Kannada · Mangalore
On track · 38% built
Land Trades Builders and Developers Private Limited
PRM/KA/RERA/1257/334/PR/051024/007130
Milestone 25
Construction
100%
as of Q1 2026-27
Sold
5
of 30
· +0 last qtr
Available
25
Adira
Construction
38%
as of Q1 2026-27
Sold
13
of 27
· +0 last qtr
Available
14
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Milestone 25
Complaints
0
on this project
Adira
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
Milestone 25
Land Trades Builders and Developers
6 other projects on K-RERA
· 1 delivered (100% complete)
· avg 61.8% complete
Adira
Land Trades Builders and Developers Private Limited
1 other project on K-RERA
· 0 delivered (100% complete)
· avg 60.0% complete
Milestone 25 — escrow account details
Adira — escrow account details
Milestone 25 — details
Adira — details