Compare / Milestone 25 vs BIMBIS

Milestone 25 vs BIMBIS

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
Delivered · 100% built
Land Trades Builders and Developers PRM/KA/RERA/1257/334/PR/220424/006823
BIMBIS
Dakshina Kannada · Mangalore
On track · 49% built
SHREE VIGNESHWARA DEVELOPERS PRM/KA/RERA/1257/334/PR/300525/007801
Milestone 25
Construction
100%
as of Q1 2026-27
Sold
5
of 30 · +0 last qtr
Available
25
BIMBIS
Construction
49%
as of Q1 2026-27
Sold
13
of 28 · +4 last qtr
Available
15
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Milestone 25
Complaints
0
on this project
BIMBIS
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
Milestone 25
Land Trades Builders and Developers
6 other projects on K-RERA · 1 delivered (100% complete) · avg 61.8% complete
BIMBIS
SHREE VIGNESHWARA DEVELOPERS
2 other projects on K-RERA · 0 delivered (100% complete) · avg 77.0% complete
Milestone 25 — escrow account details
Bank
Karnataka Bank Ltd.
Branch
Kodialbail
IFSC
KARB0000476
70% Collection A/C
4762000100194300
100% A/C
4762000100194000
30% A/C
4762000100194400
BIMBIS — escrow account details
Bank
Bank of Baroda
Branch
Bendoor
IFSC
BARB0VJBEND
70% Collection A/C
73650200001502
100% A/C
73650200001501
30% A/C
73650200000146
Milestone 25 — details
Total units
30
Total cost
₹26.69 Cr
Project start
2024-04-15
Proposed completion
2026-10-31
Address
Balmatta Mangalore
BIMBIS — details
Total units
28
Total cost
₹23.70 Cr
Project start
2025-04-01
Proposed completion
2029-03-31
Address
Bimbis Commercial and Residential Urwastores Ashok Nagar Mangalore