Compare / MAHIDHARA CMR PPR FORTUNE CITY vs THE GLENHART ESTATES PHASE 2

MAHIDHARA CMR PPR FORTUNE CITY vs THE GLENHART ESTATES PHASE 2

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
On track · 92% built
MAHIDHARA PROJECTS PRIVATE LIMITED PRM/KA/RERA/1251/308/PR/111124/007221
Active
GKS BUILDERS AND DEVELOPERS PRM/KA/RERA/1251/308/PR/101225/008325
MAHIDHARA CMR PPR FORTUNE CITY
Construction
92%
as of Q1 2026-27
Sold
of ? · +0 last qtr
Available
0
THE GLENHART ESTATES PHASE 2
No quarterly filings found for THE GLENHART ESTATES PHASE 2 yet — construction progress and sales data aren't available on K-RERA.
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
MAHIDHARA CMR PPR FORTUNE CITY
Complaints
0
on this project · 1 on MAHIDHARA PROJECTS PRIVATE LIMITED overall
THE GLENHART ESTATES PHASE 2
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
MAHIDHARA CMR PPR FORTUNE CITY
MAHIDHARA PROJECTS PRIVATE LIMITED
1 other project on K-RERA · 0 delivered (100% complete) · avg 97.0% complete · 1 complaint across those projects
THE GLENHART ESTATES PHASE 2
GKS BUILDERS AND DEVELOPERS
1 other project on K-RERA
MAHIDHARA CMR PPR FORTUNE CITY — escrow account details
Bank
ICICI Bank
Branch
Attibele
IFSC
ICIC0004388
70% Collection A/C
777705115226
100% A/C
777705115225
30% A/C
7777051125227
THE GLENHART ESTATES PHASE 2 — escrow account details
Bank
KOTAK MAHINDRA BANK
Branch
BOMMASANDRA
IFSC
KKBK0008113
70% Collection A/C
8051306461
100% A/C
8051306454
30% A/C
8051306447
MAHIDHARA CMR PPR FORTUNE CITY — details
Total cost
₹43.72 Cr
Project start
2023-10-15
Proposed completion
2026-10-30
Address
IN SY NO 13/1, 13/2 , 13/3 , 13/4 , 14/1, 14/2 , 22/1 , 23 , 27/2 , 28 , 30 , 31/1A ,47/2 , 49/1 , 49/2 OF , Chikkanahalli Village , Attibele Hobli ,Anekal Thaluk , Bangalore , Anekal , Bengaluru Urban, Karnataka - 562130
THE GLENHART ESTATES PHASE 2 — details
Total cost
₹43.83 Cr
Project start
2024-01-01
Proposed completion
2027-10-31
Address
SY NO 55/1, 55/2, 55/4, 55/5, 57/2, 61/1, 61/2, 61/4, 61/5, 62/1 AND 62/2 OF CHIKKAHAGGADE VILLAGE , KASABA HOBLI , Anekal , Bengaluru Urban, Karnataka - 562106