LIVISTA LINEA vs EKAA ARCADE
Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
LIVISTA LINEA
Dakshina Kannada · Mangalore
On track · 75% built
LIVISTA HOMES
PRM/KA/RERA/1257/334/PR/060924/007004
EKAA ARCADE
Dakshina Kannada · Mangalore
On track · 49% built
CHAITALI SHASHIDHAR SHETTY
PRM/KA/RERA/1257/333/PR/070325/007557
LIVISTA LINEA
Construction
75%
as of Q1 2026-27
Sold
10
of 24
· +4 last qtr
Available
14
EKAA ARCADE
Construction
49%
as of Q1 2026-27
Sold
3
of 20
· +0 last qtr
Available
17
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
LIVISTA LINEA
Complaints
0
on this project
EKAA ARCADE
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
LIVISTA LINEA
LIVISTA HOMES
No other K-RERA registered projects on file for this promoter.
EKAA ARCADE
CHAITALI SHASHIDHAR SHETTY
No other K-RERA registered projects on file for this promoter.
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
LIVISTA LINEA
No risk signals from filed quarters.
EKAA ARCADE
Delay risk
trending ~4 month(s) past declared completion