Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
0 complaints · 23% built
SOBHA LIMITED PRM/KA/RERA/1251/446/PR/030824/006958
0 complaints · 9% built
SOBHA LIMITED PRM/KA/RERA/1251/308/PR/230125/007419
Sobha Royal Pavilion Phase 3 - Wing 16
Construction
23%
as of Q1 2026-27
Sold
420
of 683 · +24 last qtr
Available
263
Sobha Windsor Phase 2 Wing 3, 4 and 5
Construction
9%
as of Q1 2026-27
Sold
224
of 492 · +1 last qtr
Available
268
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Sobha Royal Pavilion Phase 3 - Wing 16
Complaints
0
on this project · 222 on SOBHA LIMITED overall
Sobha Windsor Phase 2 Wing 3, 4 and 5
Complaints
0
on this project · 222 on SOBHA LIMITED overall
Builder track record
Across each promoter's other K-RERA registered projects
Sobha Royal Pavilion Phase 3 - Wing 16
SOBHA LIMITED
36 other projects on K-RERA · 8 delivered (100% complete) · avg 53.3% complete · 55 complaints across those projects
Sobha Windsor Phase 2 Wing 3, 4 and 5
SOBHA LIMITED
36 other projects on K-RERA · 8 delivered (100% complete) · avg 53.8% complete · 55 complaints across those projects
Sobha Royal Pavilion Phase 3 - Wing 16 — escrow account details
Bank
RATNAKAR BANK
Branch
Prestige Tower Residency Road
IFSC
RATN0000156
70% Collection A/C
401404199701
100% A/C
401404199700
30% A/C
401404199702
Sobha Windsor Phase 2 Wing 3, 4 and 5 — escrow account details
Bank
KOTAK MAHINDRA BANK
Branch
MG Road, Bangalore
IFSC
KKBK0008066
70% Collection A/C
0249886267
100% A/C
0249886281
30% A/C
0249886304
Sobha Royal Pavilion Phase 3 - Wing 16 — details
Total units
683
Total cost
₹1149.75 Cr
Project start
2025-09-01
Proposed completion
2031-12-31
Address
Sy No. 54/3, 55/1, 55/2, 58/1, 58/2, 58/3, 59/2, 59/3, 59/4, 59/5, 60/2, 61, 63/1 Hadosiddapura Village, and Sy. No 31/1 Chikkannelli Village
Sobha Windsor Phase 2 Wing 3, 4 and 5 — details
Total units
492
Total cost
₹1169.74 Cr
Project start
2025-08-01
Proposed completion
2031-06-30
Address