Compare / UPKAR LAKE VIEW PHASE 2 vs AHAD OPUS

UPKAR LAKE VIEW PHASE 2 vs AHAD OPUS

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
UPKAR LAKE VIEW PHASE 2
Mysore · Bengaluru South
On track · 94% built
UPKAR VENTURES PRIVATE LIMITED PRM/KA/RERA/1268/378/PR/211124/007244
AHAD OPUS
Mandya · Bengaluru South
On track · 20% built
AHAD BUILDERS PRIVATE LIMITED PRM/KA/RERA/1267/374/PR/100326/008516
UPKAR LAKE VIEW PHASE 2
Construction
94%
as of Q1 2026-27
Sold
of ? · +0 last qtr
Available
0
AHAD OPUS
Construction
20%
as of Q1 2026-27
Sold
of ? · +0 last qtr
Available
0
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
UPKAR LAKE VIEW PHASE 2
Complaints
0
on this project
AHAD OPUS
Complaints
0
on this project · 6 on AHAD BUILDERS PRIVATE LIMITED overall
Builder track record
Across each promoter's other K-RERA registered projects
UPKAR LAKE VIEW PHASE 2
UPKAR VENTURES PRIVATE LIMITED
2 other projects on K-RERA · 0 delivered (100% complete) · avg 95.0% complete
AHAD OPUS
AHAD BUILDERS PRIVATE LIMITED
11 other projects on K-RERA · 2 delivered (100% complete) · avg 100.0% complete
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
UPKAR LAKE VIEW PHASE 2
No risk signals from filed quarters.
AHAD OPUS
Delay risk construction progress far too slow to plausibly hit declared completion
UPKAR LAKE VIEW PHASE 2 — escrow account details
Bank
Karnataka Bank Ltd.
Branch
JAYANAHAR 9TH BLOCK
IFSC
KARB0000061
70% Collection A/C
0061202400000901
100% A/C
0061202400000801
30% A/C
0061202400001001
AHAD OPUS — escrow account details
Bank
HDFC
Branch
koramangala
IFSC
HDFC0000053
70% Collection A/C
50200099783314
100% A/C
50200099783314
30% A/C
50200026083624
UPKAR LAKE VIEW PHASE 2 — details
Total cost
₹6.98 Cr
Project start
2024-09-01
Proposed completion
2029-11-30
Address
SY NO 210/3 , 4 ACRE 20 GUNTAS , VARUNA VILLAGE , VARUNA HOBLI , MYSORE TALUK , MYSORE DISTRICT , MYSORE , Mysore, Karnataka - 570010
AHAD OPUS — details
Total cost
₹6.50 Cr
Project start
2023-09-20
Proposed completion
2028-03-31
Address
199/1,KODATHI VILLAGE VARTHUR HOBLI