Compare / GRC SAPPHIRE SPRING - PHASE -3 vs LS MARK IX

GRC SAPPHIRE SPRING - PHASE -3 vs LS MARK IX

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
On track · 1% built
GRC Infra Pvt. Ltd. PRM/KA/RERA/1251/310/PR/030225/007479
On track · 1% built
LIVING STRUCTURES PRM/KA/RERA/1251/308/PR/080626/008708
GRC SAPPHIRE SPRING - PHASE -3
Construction
1%
as of Q4 2025-26
Sold
—
of 52 · +0 last qtr
Available
52
LS MARK IX
Construction
1%
as of Q1 2026-27
Sold
—
of 60 · +0 last qtr
Available
60
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
GRC SAPPHIRE SPRING - PHASE -3
Complaints
0
on this project · 1 on GRC Infra Pvt. Ltd. overall
LS MARK IX
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
GRC SAPPHIRE SPRING - PHASE -3
GRC Infra Pvt. Ltd.
1 other project on K-RERA · 0 delivered (100% complete) · avg 26.0% complete
LS MARK IX
LIVING STRUCTURES
3 other projects on K-RERA · 0 delivered (100% complete) · avg 55.0% complete · 1 complaint across those projects
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
GRC SAPPHIRE SPRING - PHASE -3
No risk signals from filed quarters.
LS MARK IX
No risk signals from filed quarters.
GRC SAPPHIRE SPRING - PHASE -3 — escrow account details
Bank
Karnataka Bank Ltd.
Branch
Minerva Circle
IFSC
KARB0000062
70% Collection A/C
0062202600001901
100% A/C
0062202600001801
30% A/C
0062202600002001
LS MARK IX — escrow account details
Bank
ICICI Bank
Branch
Sarjapur
IFSC
ICIC0004387
70% Collection A/C
777705962024
100% A/C
777705962022
30% A/C
777705962026
GRC SAPPHIRE SPRING - PHASE -3 — details
Total units
52
Total cost
₹40.05 Cr
Project start
2026-06-10
Proposed completion
2030-07-31
Address
Sy no 38/1 & 38/2 situated atchoodasandra village, sarjapura hobli, anekal taluk, bangalore\, Sy no 38/1 & 38/2 situated atchoodasandra village, sarjapura hobli, anekal taluk, bangalore
LS MARK IX — details
Total units
60
Total cost
₹41.23 Cr
Project start
2026-06-01
Proposed completion
2029-12-31
Address
Sy No 7/1C and 7/1D, E Khatha No 150200101800428039, Property No 5468/7/1C/7/1D , Marsur village, Kasaba Hobli , Anekal , Bengaluru Urban, Karnataka - 562106