Compare / Soul of the Seasons - Phase 1 vs NIKHAR AVENTINO

Soul of the Seasons - Phase 1 vs NIKHAR AVENTINO

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
On track · 2% built
NBR Projects LLP PRM/KA/RERA/1251/446/PR/260226/008491
NIKHAR AVENTINO
Bengaluru Urban · Bengaluru East
No quarterly filings
NIKHAR ESTATES LLP PRM/KA/RERA/1251/446/PR/280426/008605
Soul of the Seasons - Phase 1
Construction
2%
as of Q1 2026-27
Sold
22
of 312 · +22 last qtr
Available
290
NIKHAR AVENTINO
No quarterly filings found for NIKHAR AVENTINO yet — construction progress and sales data aren't available on K-RERA.
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Soul of the Seasons - Phase 1
Complaints
0
on this project
NIKHAR AVENTINO
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
Soul of the Seasons - Phase 1
NBR Projects LLP
1 other project on K-RERA · 0 delivered (100% complete) · avg 31.0% complete
NIKHAR AVENTINO
NIKHAR ESTATES LLP
No other K-RERA registered projects on file for this promoter.
Soul of the Seasons - Phase 1 — escrow account details
Bank
HDFC
Branch
AGARA JUNCTION BRANCH BANGALORE
IFSC
HDFC0004220
70% Collection A/C
57500001910878
100% A/C
57500001912411
30% A/C
57500001912424
NIKHAR AVENTINO — escrow account details
Bank
ICICI Bank
Branch
EMBASSY TECH VILLAGE
IFSC
ICIC0005573
70% Collection A/C
557305000061
100% A/C
557305000060
30% A/C
557305000062
Soul of the Seasons - Phase 1 — details
Total units
312
Total cost
₹302.70 Cr
Project start
2026-02-01
Proposed completion
2029-11-30
Address
Survey No. 27/3 (PART), 27/6, 27/26(PART), 45/1 (PART) ofKachamaranahalli Village, , VarthurHobli, Bengaluru East Taluk , BengaluruSouth ,
NIKHAR AVENTINO — details
Total units
333
Total cost
₹293.51 Cr
Project start
2026-02-27
Proposed completion
2030-12-31
Address
SY NO. 138, NIKHAR AVENTINO, NEAR AET JUNCTION, DODDAKANNALLI, BELUNDUR, BENGALURU