Compare / Confident Meadows vs VRR GOLDEN ENCLAVE PHASE 1

Confident Meadows vs VRR GOLDEN ENCLAVE PHASE 1

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
On track · 93% built
DJ PROJECTS PRIVATE LIMITED PRM/KA/RERA/1251/308/PR/230522/004902
No quarterly filings
H N VIJAYARAGHAVA REDDY CO PRM/KA/RERA/1251/308/PR/211222/005548
Confident Meadows
Construction
93%
as of Q1 2026-27
Sold
128
of 103 · +0 last qtr
Available
13
VRR GOLDEN ENCLAVE PHASE 1
No quarterly filings found for VRR GOLDEN ENCLAVE PHASE 1 yet — construction progress and sales data aren't available on K-RERA.
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Confident Meadows
Complaints
0
on this project · 4 on DJ PROJECTS PRIVATE LIMITED overall
VRR GOLDEN ENCLAVE PHASE 1
Complaints
0
on this project · 1 on H N VIJAYARAGHAVA REDDY CO overall
Builder track record
Across each promoter's other K-RERA registered projects
Confident Meadows
DJ PROJECTS PRIVATE LIMITED
No other K-RERA registered projects on file for this promoter.
VRR GOLDEN ENCLAVE PHASE 1
H N VIJAYARAGHAVA REDDY CO
No other K-RERA registered projects on file for this promoter.
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
Confident Meadows
No risk signals from filed quarters.
VRR GOLDEN ENCLAVE PHASE 1
No risk signals from filed quarters.
Confident Meadows — escrow account details
Bank
CITY UNION BANK
Branch
kormangala
IFSC
CIUB0000109
70% Collection A/C
510909010183475
VRR GOLDEN ENCLAVE PHASE 1 — escrow account details
Bank
Karnataka Bank Ltd.
Branch
Koramangala
IFSC
KARB0000094
70% Collection A/C
0942000100220001
Confident Meadows — details
Total units
103
Total cost
₹77.21 Cr
Project start
2022-02-12
Proposed completion
2027-02-10
Address
Confident meadows, sy no 166,167/2&167/3, Yamare village sarjapura Hobli, Anekal Taluk
VRR GOLDEN ENCLAVE PHASE 1 — details
Total units
84
Total cost
₹82.29 Cr
Project start
2021-08-01
Proposed completion
2027-12-31
Address
Sy no 355, Hulimangala Village, Jigani Hobli, Anekal Taluk.