Compare / PAVANI MIRABILIA PHASE I vs TRIFECTA VANTO PHASE-1

PAVANI MIRABILIA PHASE I vs TRIFECTA VANTO PHASE-1

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
2 complaints · 84% built
Sai Sravanthi Infra Projects Pvt Ltd PRM/KA/RERA/1251/446/PR/120922/005235
On track · 87% built
TRIFECTA PROJECTS PRIVATE LIMITED PRM/KA/RERA/1251/446/PR/190424/006813
PAVANI MIRABILIA PHASE I
Construction
84%
as of Q1 2026-27
Sold
465
of 1006 · +465 last qtr
Available
643
TRIFECTA VANTO PHASE-1
Construction
87%
as of Q1 2026-27
Sold
411
of 825 · +48 last qtr
Available
414
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
PAVANI MIRABILIA PHASE I
Complaints
2
on this project · 2 on Sai Sravanthi Infra Projects Pvt Ltd overall
TRIFECTA VANTO PHASE-1
Complaints
0
on this project · 2 on TRIFECTA PROJECTS PRIVATE LIMITED overall
Builder track record
Across each promoter's other K-RERA registered projects
PAVANI MIRABILIA PHASE I
Sai Sravanthi Infra Projects Pvt Ltd
2 other projects on K-RERA · 0 delivered (100% complete) · avg 24.0% complete
TRIFECTA VANTO PHASE-1
TRIFECTA PROJECTS PRIVATE LIMITED
5 other projects on K-RERA · 1 delivered (100% complete) · avg 64.3% complete
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
PAVANI MIRABILIA PHASE I
No risk signals from filed quarters.
TRIFECTA VANTO PHASE-1
Promoter pattern 1 of 4 other projects show the same delay-risk pattern
PAVANI MIRABILIA PHASE I — escrow account details
Bank
IDFC FIRST BANK
Branch
Frazer Town
IFSC
IDFB0080168
70% Collection A/C
10094947605
TRIFECTA VANTO PHASE-1 — escrow account details
Bank
Axis Bank
Branch
Mahadevapura Branch``
IFSC
UTIB0003075
70% Collection A/C
924020044952151
100% A/C
924020044951831
30% A/C
924020045049443
PAVANI MIRABILIA PHASE I — details
Total units
1006
Total cost
₹523.69 Cr
Project start
2022-05-19
Proposed completion
2028-05-25
Address
Sy No. 22,23 & 124 SEGEHALLI , BANGALORE , Bengaluru East , Bengaluru Urban, Karnataka - 560049
TRIFECTA VANTO PHASE-1 — details
Total units
825
Total cost
₹464.62 Cr
Project start
2024-03-01
Proposed completion
2027-08-31
Address
Sy. No. 37/2,37/3,37/4,37/5,37/6,37/7P,37/8,37/9,37/10,37/11,37/12,37/13,37/14,37/15,37/16,37/17,37/18,37/19,37/20,43/4B and 43/5 , Bangalore Urban, , Bengaluru East , Bengaluru Urban, Karnataka - 560035