Compare / PAVANI MIRABILIA PHASE I vs Provident Equinox 4

PAVANI MIRABILIA PHASE I vs Provident Equinox 4

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
2 complaints · 84% built
Sai Sravanthi Infra Projects Pvt Ltd PRM/KA/RERA/1251/446/PR/120922/005235
1 complaint · 11% built
Provident Housing Limited PRM/KA/RERA/1251/310/PR/210325/007612
PAVANI MIRABILIA PHASE I
Construction
84%
as of Q1 2026-27
Sold
465
of 1006 · +465 last qtr
Available
643
Provident Equinox 4
Construction
11%
as of Q4 2025-26
Sold
627
of 756 · +17 last qtr
Available
129
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
PAVANI MIRABILIA PHASE I
Complaints
2
on this project · 2 on Sai Sravanthi Infra Projects Pvt Ltd overall
Provident Equinox 4
Complaints
1
on this project · 32 on Provident Housing Limited overall
Builder track record
Across each promoter's other K-RERA registered projects
PAVANI MIRABILIA PHASE I
Sai Sravanthi Infra Projects Pvt Ltd
2 other projects on K-RERA · 0 delivered (100% complete) · avg 24.0% complete
Provident Equinox 4
Provident Housing Limited
3 other projects on K-RERA · 0 delivered (100% complete) · avg 17.0% complete · 1 complaint across those projects
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
PAVANI MIRABILIA PHASE I
No risk signals from filed quarters.
Provident Equinox 4
No risk signals from filed quarters.
PAVANI MIRABILIA PHASE I — escrow account details
Bank
IDFC FIRST BANK
Branch
Frazer Town
IFSC
IDFB0080168
70% Collection A/C
10094947605
Provident Equinox 4 — escrow account details
Bank
ICICI Bank
Branch
Ulsoor Road
IFSC
ICIC0003904
70% Collection A/C
390405002316
100% A/C
390405002315
30% A/C
390405002317
PAVANI MIRABILIA PHASE I — details
Total units
1006
Total cost
₹523.69 Cr
Project start
2022-05-19
Proposed completion
2028-05-25
Address
Sy No. 22,23 & 124 SEGEHALLI , BANGALORE , Bengaluru East , Bengaluru Urban, Karnataka - 560049
Provident Equinox 4 — details
Total units
756
Total cost
₹540.15 Cr
Project start
2025-03-15
Proposed completion
2029-03-31
Address
Kachanayakanahalli Village, Bangalore