Compare / Sobha Dream Gardens Phase 5 - Wing 10 vs HM Scottsville

Sobha Dream Gardens Phase 5 - Wing 10 vs HM Scottsville

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
0 complaints · 77% built
SOBHA LIMITED PRM/KA/RERA/1251/309/PR/311222/005591
HM Scottsville
Bengaluru Urban · Bengaluru East
On track · 75% built
HM Infratech Private Limited PRM/KA/RERA/1251/446/PR/181224/007307
Sobha Dream Gardens Phase 5 - Wing 10
Construction
77%
as of Q1 2026-27
Sold
139
of 142 · +0 last qtr
Available
3
HM Scottsville
Construction
75%
as of Q1 2026-27
Sold
48
of 154 · +12 last qtr
Available
106
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Sobha Dream Gardens Phase 5 - Wing 10
Complaints
0
on this project · 224 on SOBHA LIMITED overall
HM Scottsville
Complaints
0
on this project · 12 on HM Infratech Private Limited overall
Builder track record
Across each promoter's other K-RERA registered projects
Sobha Dream Gardens Phase 5 - Wing 10
SOBHA LIMITED
36 other projects on K-RERA · 9 delivered (100% complete) · avg 51.9% complete · 55 complaints across those projects
HM Scottsville
HM Infratech Private Limited
No other K-RERA registered projects on file for this promoter.
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
Sobha Dream Gardens Phase 5 - Wing 10
Promoter pattern 2 of 35 other projects show the same delay-risk pattern
HM Scottsville
Delay risk trending ~18 month(s) past declared completion
Sobha Dream Gardens Phase 5 - Wing 10 — escrow account details
Bank
RATNAKAR BANK
Branch
PRESTIGE TOWERS, ( 0156 ) GROUND FLOOR, G-13, G-14, G-15 AND G-17, PRESTIGE TOWERS, 99, 100 RESIDENCY ROAD, BANGALORE
IFSC
RATN0000156
70% Collection A/C
409002401455
100% A/C
409002401431
30% A/C
409002401479
HM Scottsville — escrow account details
Bank
Axis Bank
Branch
MG Road
IFSC
UTIB0000009
70% Collection A/C
922020035352425
100% A/C
922020035352425
30% A/C
922020036267609
Sobha Dream Gardens Phase 5 - Wing 10 — details
Total units
142
Total cost
₹89.62 Cr
Project start
2023-10-01
Proposed completion
2028-12-31
Address
Balagere, Bangalore
HM Scottsville — details
Total units
154
Total cost
₹97.87 Cr
Project start
2022-01-05
Proposed completion
2027-06-30
Address
4th Main Road, 15th Cross, R T Nagar,