Compare / Mahaveer Highlands vs GREENNESTO PRIMUS

Mahaveer Highlands vs GREENNESTO PRIMUS

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
Mahaveer Highlands
Bengaluru Urban · Bengaluru South
1 complaint · 87% built
REDDY STRUCTURES PRIVATE LIMITED PRM/KA/RERA/1251/310/PR/220922/005266
GREENNESTO PRIMUS
Bengaluru Urban · Bengaluru South
1 complaint · 83% built
M/s GREENNESTO BUILDERS AND DEVELOPERS LLP PRM/KA/RERA/1251/310/PR/201022/005350
Mahaveer Highlands
Construction
87%
as of Q1 2026-27
Sold
252
of 312 · +4 last qtr
Available
60
GREENNESTO PRIMUS
Construction
83%
as of Q1 2026-27
Sold
96
of 200 · +3 last qtr
Available
104
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Mahaveer Highlands
Complaints
1
on this project · 102 on REDDY STRUCTURES PRIVATE LIMITED overall
GREENNESTO PRIMUS
Complaints
1
on this project · 3 on M/s GREENNESTO BUILDERS AND DEVELOPERS LLP overall
Builder track record
Across each promoter's other K-RERA registered projects
Mahaveer Highlands
REDDY STRUCTURES PRIVATE LIMITED
2 other projects on K-RERA · 0 delivered (100% complete) · avg 47.0% complete
GREENNESTO PRIMUS
M/s GREENNESTO BUILDERS AND DEVELOPERS LLP
No other K-RERA registered projects on file for this promoter.
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
Mahaveer Highlands
Promoter pattern 1 of 1 other projects show the same delay-risk pattern
GREENNESTO PRIMUS
No risk signals from filed quarters.
Mahaveer Highlands — escrow account details
Bank
HDFC
Branch
RICHMOND ROAD
IFSC
HDFC0000523
70% Collection A/C
57500000183941
GREENNESTO PRIMUS — escrow account details
Bank
HDFC
Branch
HSR LAYOUT
IFSC
HDFC0003758
70% Collection A/C
50200060542424
Mahaveer Highlands — details
Total units
312
Total cost
₹82.11 Cr
Project start
2022-08-01
Proposed completion
2027-03-31
Address
MAHAVEER RANCHES, SY. NO. 4/1, NAGANATHAPURA, , BEGUR HOBLI
GREENNESTO PRIMUS — details
Total units
200
Total cost
₹83.42 Cr
Project start
2023-01-13
Proposed completion
2028-07-30
Address
3/2 & 3/1B HARALUR VILLAGE, VARTHUR HOBLI, BANGALORE EAST TALUK