Compare / ISR ASHRITA vs UBER VERDANT-II

ISR ASHRITA vs UBER VERDANT-II

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
ISR ASHRITA
Bengaluru Urban · Bengaluru South
On track · 71% built
ISR CONSTRUCTIONS PVT LTD PRM/KA/RERA/1251/446/PR/211122/005489
UBER VERDANT-II
Bengaluru Urban · Bengaluru South
On track · 99% built
MANA PROJECTS PVT LTD PRM/KA/RERA/1251/446/PR/101122/005450
ISR ASHRITA
Construction
71%
as of Q1 2026-27
Sold
90
of 158 · +0 last qtr
Available
68
UBER VERDANT-II
Construction
99%
as of Q1 2026-27
Sold
123
of 202 · +0 last qtr
Available
79
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
ISR ASHRITA
Complaints
0
on this project
UBER VERDANT-II
Complaints
0
on this project · 7 on MANA PROJECTS PVT LTD overall
Builder track record
Across each promoter's other K-RERA registered projects
ISR ASHRITA
ISR CONSTRUCTIONS PVT LTD
No other K-RERA registered projects on file for this promoter.
UBER VERDANT-II
MANA PROJECTS PVT LTD
3 other projects on K-RERA · 0 delivered (100% complete) · avg 31.7% complete · 1 complaint across those projects
ISR ASHRITA — escrow account details
Bank
HDFC
Branch
RICHMOND ROAD
IFSC
HDFC0000523
70% Collection A/C
57500001058682
UBER VERDANT-II — escrow account details
Bank
KOTAK MAHINDRA BANK
Branch
Bellanduru
IFSC
KKBK0008122
70% Collection A/C
5345913718
ISR ASHRITA — details
Total units
158
Total cost
₹69.38 Cr
Project start
2022-07-26
Proposed completion
2026-08-31
Address
SORAHUNASE VILLAGE VARTHUR HOBLI BANGALORE
UBER VERDANT-II — details
Total units
202
Total cost
₹66.12 Cr
Project start
2022-10-24
Proposed completion
2026-12-31
Address
DODDAKANNELLI SARJAPUR ROAD