Compare / Seshadri Nagar vs ROYALE PROPERTIES BETHEL PHASE-05,

Seshadri Nagar vs ROYALE PROPERTIES BETHEL PHASE-05,

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
Seshadri Nagar
Chikkaballapura · Bengaluru North
Active
SRI TIRUMALA DEVELOPERS PRM/KA/RERA/1254/460/PR/220223/005734
Delivered · 100% built
Santhosh B PRM/KA/RERA/1268/378/PR/180625/007851
Seshadri Nagar
No quarterly filings found for Seshadri Nagar yet — construction progress and sales data aren't available on K-RERA.
ROYALE PROPERTIES BETHEL PHASE-05,
Construction
100%
as of Q1 2026-27
Sold
of ? · +0 last qtr
Available
0
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Seshadri Nagar
Complaints
0
on this project
ROYALE PROPERTIES BETHEL PHASE-05,
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
Seshadri Nagar
SRI TIRUMALA DEVELOPERS
No other K-RERA registered projects on file for this promoter.
ROYALE PROPERTIES BETHEL PHASE-05,
Santhosh B
No other K-RERA registered projects on file for this promoter.
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
Seshadri Nagar
No risk signals from filed quarters.
ROYALE PROPERTIES BETHEL PHASE-05,
No risk signals from filed quarters.
Seshadri Nagar — escrow account details
Bank
HDFC
Branch
Malleshwaram
IFSC
HDFC0000041
70% Collection A/C
50200076635805
ROYALE PROPERTIES BETHEL PHASE-05, — escrow account details
Bank
UCO Bank
Branch
HESARAGHATTA ROAD
IFSC
UCBA0002104
70% Collection A/C
21040210003862
100% A/C
21040210003855
30% A/C
2104021003879
Seshadri Nagar — details
Total cost
₹5.58 Cr
Project start
2018-05-11
Proposed completion
2023-09-01 overdue
Address
Survey Number 16/2, 20/2, 20/3, 20/1 , Honegullu Village, Kasaba Hobli , Chikkaballapur , Chikkaballapura, Karnataka - 562101
ROYALE PROPERTIES BETHEL PHASE-05, — details
Total cost
₹6.06 Cr
Project start
2025-06-02
Proposed completion
2027-12-31
Address