Compare / GREENNESTO PRIMUS vs South Park Phase 1

GREENNESTO PRIMUS vs South Park Phase 1

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
GREENNESTO PRIMUS
Bengaluru Urban · Bengaluru South
1 complaint · 83% built
M/s GREENNESTO BUILDERS AND DEVELOPERS LLP PRM/KA/RERA/1251/310/PR/201022/005350
South Park Phase 1
Bengaluru Urban · Bengaluru South
Delivered · 100% built
ESTEEM SOUTH PARKS PRIVATE LIMITED PRM/KA/RERA/1251/310/PR/090523/005916
GREENNESTO PRIMUS
Construction
83%
as of Q1 2026-27
Sold
96
of 200 · +3 last qtr
Available
104
South Park Phase 1
Construction
100%
as of Q1 2026-27
Sold
137
of 191 · +8 last qtr
Available
54
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
GREENNESTO PRIMUS
Complaints
1
on this project · 3 on M/s GREENNESTO BUILDERS AND DEVELOPERS LLP overall
South Park Phase 1
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
GREENNESTO PRIMUS
M/s GREENNESTO BUILDERS AND DEVELOPERS LLP
No other K-RERA registered projects on file for this promoter.
South Park Phase 1
ESTEEM SOUTH PARKS PRIVATE LIMITED
1 other project on K-RERA · 0 delivered (100% complete) · avg 99.0% complete
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
GREENNESTO PRIMUS
No risk signals from filed quarters.
South Park Phase 1
No risk signals from filed quarters.
GREENNESTO PRIMUS — escrow account details
Bank
HDFC
Branch
HSR LAYOUT
IFSC
HDFC0003758
70% Collection A/C
50200060542424
South Park Phase 1 — escrow account details
Bank
Punjab National Bank
Branch
sadashivnagar
IFSC
PUNB0108410
70% Collection A/C
1084102900000036
GREENNESTO PRIMUS — details
Total units
200
Total cost
₹83.42 Cr
Project start
2023-01-13
Proposed completion
2028-07-30
Address
3/2 & 3/1B HARALUR VILLAGE, VARTHUR HOBLI, BANGALORE EAST TALUK
South Park Phase 1 — details
Total units
191
Total cost
₹80.27 Cr
Project start
2021-07-01
Proposed completion
2026-08-15
Address
sy No 5(P), 18/2,19/3B, 19/4,19/6,19/3A (P), 19/7(P), , Gottigere Village Uttarhalli Hobli , Bengaluru South , Bengaluru Urban, Karnataka - 560097