Compare / Sir M V Layout 2 vs Athmanandhasagara-7

Sir M V Layout 2 vs Athmanandhasagara-7

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
On track · 92% built
SAHA DEVELOPERS AND PROMOTERS PRM/KA/RERA/1268/378/PR/070522/004861
On track · 99% built
ESS AND ESS INFRASTRUCTURE PRIVATE LIMITED PRM/KA/RERA/1268/378/PR/060324/006663
Sir M V Layout 2
Construction
92%
as of Q1 2026-27
Sold
—
of ? · +0 last qtr
Available
0
Athmanandhasagara-7
Construction
99%
as of Q1 2026-27
Sold
—
of ? · +0 last qtr
Available
0
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Sir M V Layout 2
Complaints
0
on this project · 5 on SAHA DEVELOPERS AND PROMOTERS overall
Athmanandhasagara-7
Complaints
0
on this project · 6 on ESS AND ESS INFRASTRUCTURE PRIVATE LIMITED overall
Builder track record
Across each promoter's other K-RERA registered projects
Sir M V Layout 2
SAHA DEVELOPERS AND PROMOTERS
11 other projects on K-RERA · 4 delivered (100% complete) · avg 98.6% complete
Athmanandhasagara-7
ESS AND ESS INFRASTRUCTURE PRIVATE LIMITED
15 other projects on K-RERA · 5 delivered (100% complete) · avg 99.4% complete
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
Sir M V Layout 2
Delay risk no completion progress across filed quarters
Promoter pattern 1 of 7 other projects show the same delay-risk pattern
Athmanandhasagara-7
Delay risk no completion progress across filed quarters
Promoter pattern 1 of 8 other projects show the same delay-risk pattern
Sir M V Layout 2 — escrow account details
Bank
Union Bank of India
Branch
Ramakrishna Nagara
IFSC
UBIN0918598
70% Collection A/C
185921010000042
Athmanandhasagara-7 — escrow account details
Bank
Union Bank of India
Branch
Ramakrishna Nagar
IFSC
UBIN0918598
70% Collection A/C
185921010000103
100% A/C
185921010000104
30% A/C
185921010000086
Sir M V Layout 2 — details
Total cost
₹6.14 Cr
Project start
2022-02-19
Proposed completion
2026-02-05 overdue
Address
Janthagalli Village, Varuna Hobli, Mysuru Taluk & Mysuru District
Athmanandhasagara-7 — details
Total cost
₹6.01 Cr
Project start
2024-02-01
Proposed completion
2027-11-27
Address
Marashettihalli Village, Varuna Hobli, Mysuru Taluk and Mysuru District.