Compare / PurpleBrick Avenue Garden - Phase 3 vs UPKAR LAKE VIEW PHASE 2

PurpleBrick Avenue Garden - Phase 3 vs UPKAR LAKE VIEW PHASE 2

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
Delivered · 100% built
PURPLEBRICK ESTATES LLP PRM/KA/RERA/1267/374/PR/130723/006067
UPKAR LAKE VIEW PHASE 2
Mysore · Bengaluru South
On track · 94% built
UPKAR VENTURES PRIVATE LIMITED PRM/KA/RERA/1268/378/PR/211124/007244
PurpleBrick Avenue Garden - Phase 3
Construction
100%
as of Q4 2025-26
Sold
of ? · +0 last qtr
Available
0
UPKAR LAKE VIEW PHASE 2
Construction
94%
as of Q1 2026-27
Sold
of ? · +0 last qtr
Available
0
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
PurpleBrick Avenue Garden - Phase 3
Complaints
0
on this project
UPKAR LAKE VIEW PHASE 2
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
PurpleBrick Avenue Garden - Phase 3
PURPLEBRICK ESTATES LLP
3 other projects on K-RERA · 2 delivered (100% complete) · avg 66.7% complete
UPKAR LAKE VIEW PHASE 2
UPKAR VENTURES PRIVATE LIMITED
2 other projects on K-RERA · 0 delivered (100% complete) · avg 95.0% complete
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
PurpleBrick Avenue Garden - Phase 3
No risk signals from filed quarters.
UPKAR LAKE VIEW PHASE 2
No risk signals from filed quarters.
PurpleBrick Avenue Garden - Phase 3 — escrow account details
Bank
KOTAK MAHINDRA BANK
Branch
M.G. Road Bangalore
IFSC
KKBK0008066
70% Collection A/C
9945181771
UPKAR LAKE VIEW PHASE 2 — escrow account details
Bank
Karnataka Bank Ltd.
Branch
JAYANAHAR 9TH BLOCK
IFSC
KARB0000061
70% Collection A/C
0061202400000901
100% A/C
0061202400000801
30% A/C
0061202400001001
PurpleBrick Avenue Garden - Phase 3 — details
Total cost
₹7.11 Cr
Project start
2023-07-10
Proposed completion
2028-06-10
Address
Sy No. 364/1,364/2,364/4 & 364/6, Belavadi village,kasaba hobli , srirangapatna taluk,mandya district-571438 , Shrirangapattna , Mandya, Karnataka - 571438
UPKAR LAKE VIEW PHASE 2 — details
Total cost
₹6.98 Cr
Project start
2024-09-01
Proposed completion
2029-11-30
Address
SY NO 210/3 , 4 ACRE 20 GUNTAS , VARUNA VILLAGE , VARUNA HOBLI , MYSORE TALUK , MYSORE DISTRICT , MYSORE , Mysore, Karnataka - 570010