Compare / Shankara Agraharam Sri Sharadamba Enclave vs BENAKA LAYOUT

Shankara Agraharam Sri Sharadamba Enclave vs BENAKA LAYOUT

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
On track · 22% built
Shankara Agraharam PRM/KA/RERA/1254/464/PR/280225/007527
BENAKA LAYOUT
Tumakuru · Bengaluru North
Delivered · 100% built
PRIYANKA S S and GEETHA C N PRM/KA/RERA/1272/394/PR/280525/007786
Shankara Agraharam Sri Sharadamba Enclave
Construction
22%
as of Q4 2025-26
Sold
—
of ? · +0 last qtr
Available
0
BENAKA LAYOUT
Construction
100%
as of Q4 2025-26
Sold
—
of ? · +0 last qtr
Available
0
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Shankara Agraharam Sri Sharadamba Enclave
Complaints
0
on this project · 4 on Shankara Agraharam overall
BENAKA LAYOUT
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
Shankara Agraharam Sri Sharadamba Enclave
Shankara Agraharam
1 other project on K-RERA
BENAKA LAYOUT
PRIYANKA S S and GEETHA C N
No other K-RERA registered projects on file for this promoter.
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
Shankara Agraharam Sri Sharadamba Enclave
Delay risk no completion progress across filed quarters
Filing overdue no update in 228 days
BENAKA LAYOUT
No risk signals from filed quarters.
Shankara Agraharam Sri Sharadamba Enclave — escrow account details
Bank
HDFC
Branch
Yelahanka
IFSC
HDFC0004228
70% Collection A/C
50200062091703
100% A/C
50200062091702
30% A/C
50200098397241
BENAKA LAYOUT — escrow account details
Bank
Industrial Development Bank of India
Branch
TUMAKURU
IFSC
IBKL0000362
70% Collection A/C
0362102000012980
100% A/C
0362102000013004
30% A/C
0362102000013013
Shankara Agraharam Sri Sharadamba Enclave — details
Total cost
₹0.81 Cr
Project start
2024-01-01
Proposed completion
2027-01-01
Address
16/2, 16/4, 18/2 Kasaba Hobli, Sanjevnaryanhalli , Gudibande Taluk, Chikkaballapur , Gudibanda , Chikkaballapura, Karnataka - 561209
BENAKA LAYOUT — details
Total cost
₹1.50 Cr
Project start
2023-01-01
Proposed completion
2026-03-31
Address
Survey No 3/5, Honnenahalli Village , Kasaba North Hobli, Tumkur Taluk , Tumakuru , Tumakuru, Karnataka - 572106