Compare / SARANG BY SUMADHURA PHASE-I vs KEERTHI NANDINI THE ASCENT

SARANG BY SUMADHURA PHASE-I vs KEERTHI NANDINI THE ASCENT

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
On track · 91% built
SUMADHURA INFRACON PRIVATE LIMITED PRM/KA/RERA/1251/446/PR/180723/006075
On track · 5% built
KEERTHI NANDINI LLP PRM/KA/RERA/1251/446/PR/170326/008533
SARANG BY SUMADHURA PHASE-I
Construction
91%
as of Q1 2026-27
Sold
181
of 272 · +2 last qtr
Available
91
KEERTHI NANDINI THE ASCENT
Construction
5%
as of Q1 2026-27
Sold
—
of 269 · +0 last qtr
Available
269
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
SARANG BY SUMADHURA PHASE-I
Complaints
0
on this project · 4 on SUMADHURA INFRACON PRIVATE LIMITED overall
KEERTHI NANDINI THE ASCENT
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
SARANG BY SUMADHURA PHASE-I
SUMADHURA INFRACON PRIVATE LIMITED
13 other projects on K-RERA · 0 delivered (100% complete) · avg 46.2% complete · 3 complaints across those projects
KEERTHI NANDINI THE ASCENT
KEERTHI NANDINI LLP
No other K-RERA registered projects on file for this promoter.
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
SARANG BY SUMADHURA PHASE-I
Promoter pattern 9 of 11 other projects show the same delay-risk pattern
KEERTHI NANDINI THE ASCENT
No risk signals from filed quarters.
SARANG BY SUMADHURA PHASE-I — escrow account details
Bank
HDFC
Branch
Richmond Road, Bangalore
IFSC
HDFC0000523
70% Collection A/C
57500001488339
KEERTHI NANDINI THE ASCENT — escrow account details
Bank
HDFC
Branch
Old Madara Road Branch
IFSC
HDFC0002047
70% Collection A/C
50200118344594
100% A/C
50200118365970
30% A/C
50200116137071
SARANG BY SUMADHURA PHASE-I — details
Total units
272
Total cost
₹238.02 Cr
Project start
2023-07-01
Proposed completion
2026-12-31
Address
BBMP Katha No 1582 Sy No 3/9 3/10 Thindlu Village Yelahanka Hobli Bangalore North Taluk
KEERTHI NANDINI THE ASCENT — details
Total units
269
Total cost
₹253.96 Cr
Project start
2026-03-01
Proposed completion
2030-02-28
Address
Sy. No. 169, Bidarahalli Hobli, Mandor Gramapanchayath, Bommenahalli Village , Bengaluru East, Bengaluru , Bengaluru East , Bengaluru Urban, Karnataka - 560049