Compare / SAI LAKSHMI LAYOUT vs Bellezea - Phase IV

SAI LAKSHMI LAYOUT vs Bellezea - Phase IV

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
On track · 96% built
V. RAJENDRA (PRAGATHI ENGINEERING WORKS) PRM/KA/RERA/1251/308/PR/220923/006284
Delivered · 100% built
NAMBIAR BUILDERS PRIVATE LIMITED PRM/KA/RERA/1251/308/PR/280324/006748
SAI LAKSHMI LAYOUT
Construction
96%
as of Q1 2026-27
Sold
of ? · +0 last qtr
Available
0
Bellezea - Phase IV
Construction
100%
as of Q4 2025-26
Sold
of ? · +0 last qtr
Available
0
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
SAI LAKSHMI LAYOUT
Complaints
0
on this project
Bellezea - Phase IV
Complaints
0
on this project · 1 on NAMBIAR BUILDERS PRIVATE LIMITED overall
Builder track record
Across each promoter's other K-RERA registered projects
SAI LAKSHMI LAYOUT
V. RAJENDRA (PRAGATHI ENGINEERING WORKS)
No other K-RERA registered projects on file for this promoter.
Bellezea - Phase IV
NAMBIAR BUILDERS PRIVATE LIMITED
No other K-RERA registered projects on file for this promoter.
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
SAI LAKSHMI LAYOUT
Delay risk trending ~23 month(s) past declared completion
Bellezea - Phase IV
No risk signals from filed quarters.
SAI LAKSHMI LAYOUT — escrow account details
Bank
Union Bank of India
Branch
HSR layout
IFSC
UBIN0911020
70% Collection A/C
110221010000056
Bellezea - Phase IV — escrow account details
Bank
KOTAK MAHINDRA BANK
Branch
Bangalore-Bellandur
IFSC
KKBK0008122
70% Collection A/C
5349633766
100% A/C
57500001366938
30% A/C
57500001368500
SAI LAKSHMI LAYOUT — details
Total cost
₹4.25 Cr
Project start
2023-02-28
Proposed completion
2026-04-01 overdue
Address
Sy No. 32/3, 35, 36/2 at Anekal Gramantara, Kasaba Hobli , Anekal Taluk, Bangalore Urban District, , Anekal , Bengaluru Urban, Karnataka - 562106
Bellezea - Phase IV — details
Total cost
₹3.69 Cr
Project start
2023-05-01
Proposed completion
2027-05-01
Address
SARJAPURA HOBLI, ANEKAL, BENGALURU URBAN