Compare / Assetz Inspira Melodies of Life vs Assetz Mizumi Reserve Tower A3 A5

Assetz Inspira Melodies of Life vs Assetz Mizumi Reserve Tower A3 A5

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
On track · 97% built
IINSPIRA WORLDCITY PROJECTS PRIVATE LIMITED PRM/KA/RERA/1251/310/PR/300124/006594
On track · 49% built
APG COMMUNITY DEVELOPMENT PRIVATE LIMITED PRM/KA/RERA/1251/308/PR/130526/008650
Assetz Inspira Melodies of Life
Construction
97%
as of Q1 2026-27
Sold
—
of ? · +0 last qtr
Available
0
Assetz Mizumi Reserve Tower A3 A5
Construction
49%
as of Q1 2026-27
Sold
6
of 264 · +6 last qtr
Available
258
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Assetz Inspira Melodies of Life
Complaints
0
on this project
Assetz Mizumi Reserve Tower A3 A5
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
Assetz Inspira Melodies of Life
IINSPIRA WORLDCITY PROJECTS PRIVATE LIMITED
1 other project on K-RERA · 0 delivered (100% complete) · avg 15.0% complete
Assetz Mizumi Reserve Tower A3 A5
APG COMMUNITY DEVELOPMENT PRIVATE LIMITED
1 other project on K-RERA · 0 delivered (100% complete) · avg 54.0% complete
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
Assetz Inspira Melodies of Life
Promoter pattern 1 of 1 other projects show the same delay-risk pattern
Assetz Mizumi Reserve Tower A3 A5
No risk signals from filed quarters.
Assetz Inspira Melodies of Life — escrow account details
Bank
HDFC
Branch
Richmond Circle
IFSC
HDFC0000523
70% Collection A/C
57500001008672
100% A/C
57500001008222
30% A/C
57500001008212
Assetz Mizumi Reserve Tower A3 A5 — escrow account details
Bank
ICICI Bank
Branch
Kumara Park Banaglore
IFSC
ICIC0006253
70% Collection A/C
625305019942
100% A/C
625305019941
30% A/C
625305019943
Assetz Inspira Melodies of Life — details
Total cost
₹517.90 Cr
Project start
2024-03-01
Proposed completion
2026-08-31 overdue
Address
SY. NO-86/1, 86/ 3, 86/ 4, 2/ 1, 2/ 2, 4, 5, 7 ,8/ 1, 8/ 2, 8/ 3, 9, 10 13/ 2, 13/ 3, 14/ 1, 14/ 2, 14/ 3, 15/ 1, 15/ 2, 15/ 3, 16, 17/ 1 , AT K.G. CHOODASANDRA VILLAGE, 120/ 1 and 120/ 3 120/ 4 . AT RAYASANDRA VILLAGE,SARJAPURA HOBLI, ANEKAL TALUK, BANGALORE , Bengaluru South , Bengaluru Urban, Karnataka - 560099
Assetz Mizumi Reserve Tower A3 A5 — details
Total units
264
Total cost
₹506.66 Cr
Project start
2026-04-01
Proposed completion
2031-03-31
Address
AT SY.NO.5/4, 5/5, 173/1, 173/2, 175, 176, 177/1, 177/2, 178, 179/1, 179/2, 180/1, 180/2, 180/3, 187/1, 203 OF KUDLU VILLAGE , AND SY.NO. 5/1 (OLD NO - 5), 6, 7,8/1, 8/4, 8/5 OF PARAPPANA AGRAHARA VILLAGE, BEGUR HOBLI, ANEKAL TALUK, BENGALURU. , Anekal , Bengaluru Urban, Karnataka - 560068