Compare / SOBHA Crystal Meadows Phase 2 Wing 7 and 8 vs RADIANCE PLATINUM

SOBHA Crystal Meadows Phase 2 Wing 7 and 8 vs RADIANCE PLATINUM

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
0 complaints · 0% built
SOBHA LIMITED PRM/KA/RERA/1251/446/PR/280324/006734
RADIANCE PLATINUM
Bengaluru Urban · Bengaluru North
On track · 78% built
Radiance Realty Developers India Limited PRM/KA/RERA/1251/310/PR/060824/006962
SOBHA Crystal Meadows Phase 2 Wing 7 and 8
Construction
0%
as of Q4 2025-26
Sold
—
of 59 · +0 last qtr
Available
59
RADIANCE PLATINUM
Construction
78%
as of Q1 2026-27
Sold
60
of 62 · +1 last qtr
Available
2
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
SOBHA Crystal Meadows Phase 2 Wing 7 and 8
Complaints
0
on this project · 224 on SOBHA LIMITED overall
RADIANCE PLATINUM
Complaints
0
on this project · 1 on Radiance Realty Developers India Limited overall
Builder track record
Across each promoter's other K-RERA registered projects
SOBHA Crystal Meadows Phase 2 Wing 7 and 8
SOBHA LIMITED
36 other projects on K-RERA · 9 delivered (100% complete) · avg 54.1% complete · 55 complaints across those projects
RADIANCE PLATINUM
Radiance Realty Developers India Limited
No other K-RERA registered projects on file for this promoter.
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
SOBHA Crystal Meadows Phase 2 Wing 7 and 8
Promoter pattern 2 of 35 other projects show the same delay-risk pattern
RADIANCE PLATINUM
No risk signals from filed quarters.
SOBHA Crystal Meadows Phase 2 Wing 7 and 8 — escrow account details
Bank
Axis Bank
Branch
MG Road, Bangalore
IFSC
UTIB0000009
70% Collection A/C
923020012829828
100% A/C
923020012829884
30% A/C
923020012829877
RADIANCE PLATINUM — escrow account details
Bank
HDFC
Branch
Hennur Road
IFSC
HDFC0002815
70% Collection A/C
57500001464530
100% A/C
57500001464731
30% A/C
00040350011230
SOBHA Crystal Meadows Phase 2 Wing 7 and 8 — details
Total units
59
Total cost
₹348.46 Cr
Project start
2024-08-01
Proposed completion
2031-06-30
Address
Sy No. 107(P), 115/2, 115/3, 115/4, 115/5, 116/3 situated at Nagondanahalli village and Sy No. 30/1, 30/6, Situated at Hagadur Village, K.R.Puram Hobli
RADIANCE PLATINUM — details
Total units
62
Total cost
₹166.15 Cr
Project start
2024-09-01
Proposed completion
2029-08-31
Address