Compare / AFTER THE RAIN COMMERCIAL vs SOBHA Crystal Meadows Phase 2 Wing 7 and 8

AFTER THE RAIN COMMERCIAL vs SOBHA Crystal Meadows Phase 2 Wing 7 and 8

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
3 complaints · 21% built
Total Environment Building Systems Private limited. PRM/KA/RERA/1251/309/PR/110522/004867
0 complaints · 0% built
SOBHA LIMITED PRM/KA/RERA/1251/446/PR/280324/006734
AFTER THE RAIN COMMERCIAL
Construction
21%
as of Q1 2026-27
Sold
38
of 38 · +11 last qtr
Available
0
SOBHA Crystal Meadows Phase 2 Wing 7 and 8
Construction
0%
as of Q4 2025-26
Sold
—
of 59 · +0 last qtr
Available
59
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
AFTER THE RAIN COMMERCIAL
Complaints
3
on this project · 3 on Total Environment Building Systems Private limited. overall
SOBHA Crystal Meadows Phase 2 Wing 7 and 8
Complaints
0
on this project · 224 on SOBHA LIMITED overall
Builder track record
Across each promoter's other K-RERA registered projects
AFTER THE RAIN COMMERCIAL
Total Environment Building Systems Private limited.
No other K-RERA registered projects on file for this promoter.
SOBHA Crystal Meadows Phase 2 Wing 7 and 8
SOBHA LIMITED
36 other projects on K-RERA · 9 delivered (100% complete) · avg 54.1% complete · 55 complaints across those projects
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
AFTER THE RAIN COMMERCIAL
Delay risk no completion progress across filed quarters
Escrow 1 quarter(s) withdrawn with no matching progress
SOBHA Crystal Meadows Phase 2 Wing 7 and 8
Promoter pattern 2 of 35 other projects show the same delay-risk pattern
AFTER THE RAIN COMMERCIAL — escrow account details
Bank
KOTAK MAHINDRA BANK
Branch
Bangalore MG Road
IFSC
KKBK0008066
70% Collection A/C
5345910779
SOBHA Crystal Meadows Phase 2 Wing 7 and 8 — escrow account details
Bank
Axis Bank
Branch
MG Road, Bangalore
IFSC
UTIB0000009
70% Collection A/C
923020012829828
100% A/C
923020012829884
30% A/C
923020012829877
AFTER THE RAIN COMMERCIAL — details
Total units
38
Total cost
₹308.04 Cr
Project start
2022-05-01
Proposed completion
2028-05-01
Address
Survey no 32 part1 and 33 part 1 and 33 part 2 Kanakapura Road, Tallaghattapura
SOBHA Crystal Meadows Phase 2 Wing 7 and 8 — details
Total units
59
Total cost
₹348.46 Cr
Project start
2024-08-01
Proposed completion
2031-06-30
Address